  1. 21 Jun 2001

    Mansoor Abdmoulaie to Michelle Lokay and 4 more

    TW/ Conoco in Lea County, NM

    This is a follow up to our meeting of 6-13-2001 TW/ Conoco project in Lea County, NM. The following is a summary of the facility requirements and a level "A" cost estimat…

  2. 12 Jun 2001

    Mansoor Abdmoulaie to Michelle Lokay and 4 more

    Conoco/TW at Monument--- level "A" +/- 30% cost estimate

    Design volume=60 mmcf/d at 700 psig The following is a summary of facility requirements and the associated cots to tie Conoco to TW-10" suction side of the Monument Compr…

  3. 8 Jun 2001

    Mansoor Abdmoulaie to Kevin Hyatt and 10 more

    RE: ConocoProjReqForm.xls/ Monument System

    The existing capacity of this system is 38 mmcf/d. Now that we know where the exactl location of the tie-in is and based on your input I have created two flow modeling op…

  4. 1 Jun 2001

    Mansoor Abdmoulaie to Perry Frazier and 2 more

    Keystone capacity

    The Keystone capacity at 500 psig suction pressure & 800 psig discharge pressure Summer: 95 mmcf/d Winter 100 mmcf/d Mansoor

  5. 18 May 2001

    Mansoor Abdmoulaie to Michelle Lokay and 6 more

    New Supply Opportunity

    Michelle I have checked the location of the Wizard#1 well. According to the legal description, the well is located approximately 6 miles north of WT-1. I have listened to…

  6. 16 May 2001

    Mansoor Abdmoulaie to Kevin Hyatt and 2 more

    TW/ Questar interconnects in two locations

    FYI and also I will get back with you within a week. Mansoor

  7. 10 May 2001

    Mansoor Abdmoulaie to Kevin Hyatt and 4 more

    Cost Estimate for MAOP facility requirements

    Kevin I have completed the following costs for the MAOP facility requirements project but have not completed yet the cost of 55,90 and 115 mmcf/d alternatives on the San …

  8. 10 Apr 2001

    Mansoor Abdmoulaie to Kevin Hyatt and 8 more

    TW/ Agave---Atoka-3 capacity

    This is in response to our meeting of April-10-2001 in Midland with Agave. Assuming units #761 and #762 are now assigned to LEC-10" service, the below schematic is showin…

  9. 5 Apr 2001

    Mansoor Abdmoulaie to Lorraine Lindberg and 30 more

    TW-West Texas Expansion Level "A" release cost estimate 4/5/2001

    This is in response to your request of 3-26-2001 regarding the expansion of TW pipeline system in West Texas. Current Facility Capacity Summary Compression capacity at WT…

  10. 3 Apr 2001

    Mansoor Abdmoulaie to Kevin Hyatt and 8 more

    New Compressor Station in Eddy County, NM.

    As I mentioned the other day, one of the possible ways to receive high volume of gas from our customers is to design and construct new compression facilities adjacent to …

  11. 27 Mar 2001

    Mansoor Abdmoulaie to Lorraine Lindberg and 6 more

    TW/ BP in Eddy County, NM.

    This is a level "A" cost estimate (?30%) to tie BP's gas to TW high-pressure line in Eddy County NM. A) 30 mmcf/d case (BP pressure=1000 psig): 13 miles of 10" (OD) pipel…

  12. 22 Feb 2001

    Mansoor Abdmoulaie to Kevin Hyatt and 18 more

    TW/ Agave ----meeting of Feb-8-2001

    Kevin This is a summary of my response to the meeting of Feb-8-2001 with Agave in Houston. Please, let me know if am missing any thing from that meeting. Also please let …