Enron email

Algorithmic Indexing

10 Apr 2001, 18:20 UTC

TW/ Agave---Atoka-3 capacity

From
Mansoor Abdmoulaie mansoor.abdmoulaie@enron.com
To
Kevin Hyatt
Cc
Arnie Bailey, Bob Burleson, Darrell Schoolcraft, Perry Frazier
Bcc
Arnie Bailey, Bob Burleson, Darrell Schoolcraft, Perry Frazier
Date
Tue, 10 Apr 2001 11:20:53 -0700 (PDT)
This is in response to our meeting of April-10-2001 in Midland with Agave.

Assuming units #761 and #762 are now assigned to LEC-10" service, the below schematic is showing the capacity of the three remaining units #822, #842 and #845 at Atoka-3.

At suction pressure of 225 psig and discharge pressure of 560 psig the capacity is 36 mmcf/d.  






The 36 mmcf/d is not a fixed capacity, if discharge pressure increases the capacity decreases. Basically it depends on the volume activities between Atoka-3 and Atoka-1 such as BP, Rio Pecos and GPM.
Please pass this on to Agave.

If you have any questions please call.