This is a level "A" cost estimate (?30%) to tie BP's gas to TW high-pressure line in Eddy County NM.

A)      30 mmcf/d case (BP pressure=1000 psig):
13 miles of 10" (OD) pipeline and interconnect facilities at an estimated cost of $3,600,000.





B)     75 mmcf/d case (BP pressure =1000 psig):

Option-1): 13 miles of 16"(OD) and interconnect facilities at an estimated cost of $6,000,000.  



Option-2): 13 miles of 10", interconnect facilities and a 600-hp unit at an estimated cost of
                     $4,700,000.     








If you have any questions please call me.