  I have completed the following costs for the MAOP facility requirements project but have not completed yet the cost of 55,90 and 115 mmcf/d alternatives on
 the San Juan Lateral. Presently Working with Engineering on this project.
 Mansoor
Quoted or forwarded from earlier messages
---------------------- Forwarded by Mansoor Abdmoulaie/ET&S/Enron on 05/10/2001 03:36 PM ---------------------------


Mansoor Abdmoulaie
05/09/2001 03:32 PM
To:	Morgan Gottsponer/ET&S/Enron
cc:	Eric Faucheaux/ET&S/Enron@Enron, Perry Frazier/ET&S/Enron@ENRON, Earl Chanley/ET&S/Enron@ENRON 

Subject:	Cost Estimate for MAOP facility requirements

 			
		Level-A Cost Estimate


	Cost to replace 30" mainline valve assy with blowdowns and asso piping:
	$210,000.0
*Gas lost is not included in the cost if blow down required.


	Cost to do a 30" stopple project:
	$100,000.0
	*By-pass is not required for stoppling activities.
	*One stopple fitting only.
	*Gas loss not included in the cost if blow down required.

	Cost/ mile to replace 30" pipe that would meet class- 3 requirements: 
	$1,166,000 to $1,475,000 (loop with existing).