	This is a follow up to our meeting of 6-13-2001 TW/ Conoco project in Lea County, NM.	
	The following is a summary of the facility requirements and a level "A" cost estimate ( 30% +/-) for the following alternatives:


	1) 12 mmcf/d ( Section 24-R35E-T20S) 6 miles away from Monument

		Facility requiremsts:	10x 6" Tee, valve, orfice meter, Proportional Sampler and H2s/ H2s Monitors, EFM, communication facilities
					and  control valves.
					Costs= $235,000
					         =	$310,000 ( with 32% Tax gross-up) 

	 

	

	2) 14 mmcf/d ( Section 27-R35E-T20S) 4 miles away from Monument

		Facility requirements:	The same as alternative-1. 
	
	 

	3) 18 mmcf/d ( at the Monument Compressor Station) :

		Facility requirements:	10x 8" Tee, valve, orfice meter, Proportional Sampler, 
					communication facilities, EFM, H2s& H2o monitors 
					and control valves.
					
					Costs=$275,000	
					        = $363,000 ( with 32% tax gross-up)

		 			