to:mbrown9@enron.com means mbrown9@enron.com.
-
14 Jul 2001
Howard Fromer to Kevin M Presto, Mark Dana Davis, jeff.ader@enron.com and 68 more
NY RTO Order
Attached is a summary of the New York RTO Order issued by FERC late yesterday. I apologize for the length, but I wanted to include a number of quotes from the Order that …
-
13 Jul 2001
Howard Fromer to Kevin M Presto, Mark Dana Davis, jeff.ader@enron.com and 67 more
NY RTO Order
Attached is a summary of the New York RTO Order issued by FERC late yesterday. I apologize for the length, but I wanted to include a number of quotes from the Order that …
-
13 Jul 2001
Sarah Novosel to Kevin M Presto, Mark Dana Davis, jeff.ader@enron.com and 60 more
PJM RTO Order
Attached is a summary of the PJM RTO order. While it is somewhat lengthy, the order has a lot of good information in it that I wanted to share with the group, particularl…
-
13 Jul 2001
Sarah Novosel to Kevin M Presto, Mark Dana Davis, jeff.ader@enron.com and 59 more
PJM RTO Order
Attached is a summary of the PJM RTO order. While it is somewhat lengthy, the order has a lot of good information in it that I wanted to share with the group, particularl…
-
12 Jul 2001
Sarah Novosel to Kevin M Presto, Mark Dana Davis, jeff.ader@enron.com and 38 more
FERC Meeting on Northeast RTO
FERC held its meeting today. Big things happened. Northeast FERC approves PJM conditionally as the RTO "platform" to be used to form one RTO in the northeast. FERC reject…
-
11 Jul 2001
Sarah Novosel to Richard Shapiro, Linda Robertson, James D Steffes and 93 more
Re: FERC Agenda
FERC has already stricken some items off of its agenda (the meeting begins in about 30 minutes). The stricken items are: The Portland General and EPMI filings to allow PG…
-
11 Jul 2001
Sarah Novosel to Kevin M Presto, Mark Dana Davis, jeff.ader@enron.com and 38 more
FERC Meeting on Northeast RTO
FERC held its meeting today. Big things happened. Northeast FERC approves PJM conditionally as the RTO "platform" to be used to form one RTO in the northeast. FERC reject…
-
11 Jul 2001
Sarah Novosel to Richard Shapiro, Linda Robertson, James D Steffes and 93 more
Re: FERC Agenda
FERC has already stricken some items off of its agenda (the meeting begins in about 30 minutes). The stricken items are: The Portland General and EPMI filings to allow PG…
-
11 Jul 2001
Donna Fulton to Sarah Novosel and 88 more
Re: FERC Agenda
Sarah Novosel and I are hearing rumors from the FERC that the two new RTO dockets on the agenda for tomorrow may be orders in the Northeast RTOs and the Southeast RTOs re…
-
10 Jul 2001
Donna Fulton to Sarah Novosel and 88 more
Re: FERC Agenda
Sarah Novosel and I are hearing rumors from the FERC that the two new RTO dockets on the agenda for tomorrow may be orders in the Northeast RTOs and the Southeast RTOs re…
-
28 Jun 2001
Sarah Novosel to Kevin M Presto, Mark Dana Davis, jeff.ader@enron.com and 38 more
FERC Order on NYISO AMP Filing
The Commission approved the NYISO's AMP proposal for Summer 2001, expiring on October 31, 2001. The Commission acknowledges problems with the proposal, such as 1) the AMP…
-
4 Jun 2001
Sarah Novosel to Kevin M Presto, Mark Dana Davis, jeff.ader@enron.com and 38 more
PJM Orders
The Commission issued a couple of orders in PJM last week: PJM,s Load Response Program: FERC approved implementation of two load response pilot programs proposed by PJM …
-
24 May 2001
Sarah Novosel to Kevin M Presto, Mark Dana Davis, jeff.ader@enron.com and 37 more
NSTAR Complaint and Northeast RTOs
On May 14, NSTAR filed a complaint against Sithe and PG&E Trading, arguing that both have generation market power in the Northeastern Massachusetts Area (NEMA) during tim…
-
10 May 2001
Sarah Novosel to Kevin M Presto, Mark Dana Davis, jeff.ader@enron.com and 35 more
Mirant Order
Yesterday evening, FERC issued an order granting Mirant's complaint against the ISO's plans to implement the Circuit Breaker proposal without FERC approval. The Commissio…
-
9 May 2001
Sarah Novosel to Kevin M Presto, Mark Dana Davis, jeff.ader@enron.com and 35 more
New York Orders on Bid Caps and TEP Authority
FERC issued orders last night in the two New York dockets regarding extension of NYISO's $1,000 bid cap and extension of the ISO's TEP authority. FERC grants extension of…
-
9 May 2001
Howard Fromer to Tom May and 72 more
Re: FERC Orders
Actually, it sounds like NE has adopted NY's EXISTING market monitoring plan. The proposed NY "circuit breaker" would "automate" the current process and implement the mit…
-
8 May 2001
Tom May to Sarah Novosel and 74 more
Re: FERC Orders
In regard to the market monitoring issue below, this effectively adopts NY's circuit breaker proposal for mitigation. FERC's approval leaves little hope to overturn this …
-
8 May 2001
Sarah Novosel to Kevin M Presto, Mark Dana Davis, jeff.ader@enron.com and 35 more
FERC Orders
The following are a few summaries of recent New England orders. Please let us know if you have any questions. Sarah FERC Approves NEPOOL's Three-Part Bids On April 25, FE…
-
29 Mar 2001
Sarah Novosel to Kevin M Presto, Mark Dana Davis, jeff.ader@enron.com and 33 more
New England and PJM Announce Standard Market Design
In case you all have not seen this, here is a press release on an agreement between New England and PJM to develop a standardize market design based on PJM's market desig…
-
16 Mar 2001
Sarah Novosel to Kevin M Presto, Mark Dana Davis, jeff.ader@enron.com and 32 more
New York Regulatory Summary
Attached is a memo from Howard Fromer, Kathleen Sullivan and me regarding regulatory issues in New York. Also attached are presentations Enron has made recently. Please l…