FERC Order on NYISO AMP Filing

From
Sarah Novosel sarah.novosel@enron.com
To
Kevin M Presto, Mark Dana Davis, jeff.ader@enron.com, Edward Baughman, joe.gordon@enron.com, Janelle Scheuer, mbrown9@enron.com, Mark Bernstein, John Llodra, George Wood, Paul J Broderick, jason.thompkins@enron.com
and 29 more Mason Hamlin, Robert Stalford, Tom May, Gautam Gupta, Narsimha Misra, Steve Montovano, Garrett Tripp, berney.aucoin@enron.com, Rob Wheeler, Rogers Herndon, Jim Meyn, Aleck Dadson, Daniel Allegretti, Pearce W Hammond, Joe Hartsoe, Donna Fulton, Howard Fromer, Kathleen Sullivan, Tom Hoatson, Thane Twiggs, Sarah Novosel, Christi L Nicolay, James D Steffes, Linda Robertson, Richard Shapiro, Steven J Kean, Charles Decker, Nick Politis, sscott3@enron.com
Date
Thu, 28 Jun 2001 10:09:00 -0700 (PDT)
The Commission approved the NYISO's AMP proposal for Summer 2001, expiring on 
October 31, 2001.  The Commission acknowledges problems with the proposal, 
such as  1) the AMP may mitigate bids when market power was not the cause of 
the high bid,  and 2) generators will not have a chance to explain their bids 
prior to mitigation.  Nevertheless, FERC still approves the proposal, 
justifying its actions by saying that the proposal is only temporary.

The Commission notes that, while it prefers more limited automatic mitigation 
procedures (where market power mitigation is tied to structural market power 
problems), it will accept the NY proposal for this summer because NY is 
concerned that supplies will be tight and demand response may not be 
effective.

A copy of  the order is attached.  Please let us know if you have any 
questions.

Sarah