  1. 25 Feb 2002

    John Sturn to Ben Asante, Gary Choquette, Jerry Graves and 12 more

    Bloomfield DRA Re-Application

    Please note below, information on the conference call to discuss re-apply drag reducing agent to the Bloomfield to LaPlata line. Talk with you then. Thanks, John

  2. 22 Feb 2002

    John Sturn to Ben Asante, Gary Choquette, Jerry Graves and 11 more

    Bloomfield DRA Re-Application

    I have been asked to proceed with plans for the installation of DRA on the SJ lateral for around mid-April. I am trying to schedule a conference call next week to discuss…

  3. 14 Feb 2002

    Jerry Graves to Team San-Juan-LaPlata and 10 more

    RE: La Plata Unit Fuel Valve Change-out

    I'll add the "fuel valve change out" to the scope of work to be done at that time. Jerry

  4. 14 Feb 2002

    Team San-Juan-LaPlata to Jerry Graves and 10 more

    RE: La Plata Unit Fuel Valve Change-out

    The fuel valve replacement is scheduled for April 2nd, in order to accommodate everyone's schedule, contractors, Solar representatives, regional field engineers, etc.. Th…

  5. 12 Feb 2002

    Jerry Graves to Gary Choquette, David Roensch, Team San-Juan-LaPlata and 5 more

    RE: La Plata Unit Fuel Valve Change-out

    I don't have an outage for fuel valve replacement yet. Would that need to be done during the scheduled turn around? Jerry

  6. 12 Feb 2002

    Todd Ingalls to Gary Choquette, David Roensch, Team San-Juan-LaPlata and 6 more

    RE: La Plata Unit Fuel Valve Change-out

    Nowhere Yet. I still have it on my plans to do. Todd

  7. 11 Feb 2002

    David Roensch to Ben Asante, Darrell Schoolcraft, Ron Matthews and 4 more

    RE: San Juan Pig

    A conf. call has been set up for Tuesday February 12th at 9:00 A.M. Central time. 877-795-3687 pin 346994 10 ports will be available

  8. 9 Feb 2002

    David Roensch to Ben Asante, Jeff Whippo, John Sturn and 3 more

    RE: San Juan Pig

    I would like to schedule a conf. call to discuss this next week (Tuesday?) if you all would be available. Let me know and I will make the arrangements. Thanks

  9. 8 Feb 2002

    Ben Asante to Ron Matthews, Lindy Donoho and 4 more

    RE: TW History

    Good Ron, very good.

  10. 8 Feb 2002

    Ron Matthews to Lindy Donoho and 6 more

    TW History

    This is very lengthy but the best I can do in a rush. Didn't have time to research all of the times and miles of pipe but did the best I could. If we need the details, le…

  11. 8 Feb 2002

    Ben Asante to David Roensch and 12 more

    RE: San Juan Pig

    David, Here is our efficiency analysis from the online model. This is just for the Bisti to Gallup section. The other sections have comparable results. You can see that b…

  12. 1 Feb 2002

    Dennis Alters to Gary Choquette and 4 more

    TW Fuel Report

    Gary, Can you please provide David the fuel report as requested. Thanks Dennis Dennis, can we get a copy of the TW Fuel Report in the field?

  13. 24 Jan 2002

    Ben Asante to Ben Asante, John Sturn, Mansoor Abdmoulaie and 79 more

    ETS Optimization - Weekly Report (24 Jan)

    Please find attached the weekly report for ETS Optimization up to 01/24/02. Ben Asante

  14. 8 Jan 2002

    Jerry Graves to Jerry Graves, c..alexander@enron.com, Lynn Blair and 72 more

    RE: Outage Commercial Review Meeting (NNG, TW & NBPL)

    The Stan Horton all employee meeting in Omaha is scheduled during the same time period as this meeting. If you are attending that meeting don't worry about getting to thi…

  15. 8 Jan 2002

    Jerry Graves to c..alexander@enron.com, Lynn Blair, mike.bonnstetter@enron.com and 72 more

    Outage Commercial Review Meeting (NNG, TW & NBPL)

    FYI, The next Outage Coordination Commercial Review meeting is 01/09/02. The purpose for the meeting is to discuss outages that have a flow impact for the month of Februa…

  16. 20 Dec 2001

    David Roensch to ben.tanner@enron.com, scott.hill@enron.com, Russ Ulibarri and 20 more

    RE: preliminary report

    Ben, we had discussions with Citizens this morning concerning the Griffith interconnect. Citizens has requested that we modify our controls so that we convert to a pressu…

  17. 18 Dec 2001

    Darrell Schoolcraft to David Roensch, Kimberly Watson, Sarabeth Smith and 3 more

    FW: Requested pressure cut at Citizens Griffith TW Interconnect

    This is an email sent to me after my conversation with Rob last week. I don't know where he is leading with this. However will every one please read the below and Jerry i…

  18. 14 Dec 2001

    Jerry Graves to c..alexander@enron.com, Lynn Blair, mike.bonnstetter@enron.com and 72 more

    Outage Commercial Review Schedule (2002)

    FYI, Here is the 2002 schedule for the Outage Commercial Review Meeting. Note the new locations and the new conference code number. These dates have been set, but are sub…

  19. 13 Dec 2001

    Lorna Brennan to bret.fritch@enron.com, Donna Martens, Keith Petersen and 98 more

    NGI Article on Trailblazer Sale to KMP

    Kinder Morgan to Buy Enron's Share of Trailblazer Kinder Morgan Energy Partners L.P. announced Wednesday it has signed a definitive agreement with Enron Trailblazer Pipel…

  20. 13 Dec 2001

    Darrell Schoolcraft to David Roensch, Rich Jolly, Kimberly Watson and 8 more

    FW: preliminary report

    Below is a perliminary report that Citizens sent and their recommendation. Please note Rob's message. Gary will you and Tiny review the report and next week we can set a …

  21. 12 Dec 2001

    Ben Asante to David Roensch, bob.mcchane@enron.com, Ron Matthews and 10 more

    RE: FW: La Plata to Bloomfield

    Thanks Rich, Tiny and the san Juan team. We appreciate your prompt response. ben

  22. 6 Dec 2001

    Arnold L. Eisenstein to Larry F. Campbell, William Kendrick, Ruth Jensen and 7 more

    FW: EngineTest.xls

    This is the GG (jet) for Unit 2 on Red Rock also - look at the range and fuel rate at turndown

  23. 4 Dec 2001

    Lorna Brennan to Courtney Barker, Mike W. McGowan, ken.anderson@enron.com and 84 more

    WSI Updates Their Weather Forecast

    Note: The track record for WSI seems to have been better than the CPC for the past few winters. Breaking News : posted Dec 4, 11:50 AM WSI Predicts Warmer-than-Normal Win…

  24. 26 Nov 2001

    Lorna Brennan to Courtney Barker, Mike W. McGowan, ken.anderson@enron.com and 95 more

    CERA Report: Drilling Activity Downturn Means Tighter Gas Supply

    Attached is the CERA report entitled "Drilling Activity Downturn Means Tighter Gas Supply". A short synopsis: FALLING GAS PRICES TRIGGER ACTIVE RIG COUNT DECLINE The econ…

  25. 23 Nov 2001

    Rich Jolly to John Sturn, David Roensch, Kimberly Watson and 21 more

    RE: La Plata to Bloomfield Drag Reducing Agent Application Evaluation - No Go

    Thanks to all for helping to evaluate and come to an agreement on this project. Maybe sometime later we'll get another chance to look at it . RJ