14 Feb 2002, 18:42 UTC
RE: La Plata Unit Fuel Valve Change-out
- From
- Jerry Graves jerry.graves@enron.com
- Date
- Thu, 14 Feb 2002 10:42:44 -0800 (PST)
I'll add the "fuel valve change out" to the scope of work to be done at that time. Jerry
Quoted or forwarded from earlier messages
-----Original Message----- From: San-Juan-LaPlata, Team Sent: Thursday, February 14, 2002 12:33 PM To: Graves, Jerry Cc: Choquette, Gary; Roensch, David; Ingalls, Todd; Schoolcraft, Darrell; Asante, Ben Subject: RE: La Plata Unit Fuel Valve Change-out The fuel valve replacement is scheduled for April 2nd, in order to accommodate everyone's schedule, contractors, Solar representatives, regional field engineers, etc.. This will coincide with our annual turnaround, which is scheduled for April 2nd through the 5th. Unit A-102 is currently running in the normal solonox mode to prevent any compliance issues, but is being operated at a reduced RPM. Hopefully this will satisfy all interests until repairs can be made. If you have any questions, please call us @ (970) 259-8238. From: Jerry Graves/ENRON@enronXgate on 02/12/2002 12:34 PM CST To: Gary Choquette/ENRON@enronXgate, David Roensch/ET&S/Enron@ENRON, Team San-Juan-LaPlata/ET&S/Enron@ENRON, Todd Ingalls/ENRON@enronxgate cc: Darrell Schoolcraft/ENRON@enronXgate, Ben Asante/ENRON@enronXgate Subject: RE: La Plata Unit Fuel Valve Change-out I don't have an outage for fuel valve replacement yet. Would that need to be done during the scheduled turn around? Jerry -----Original Message----- From: Choquette, Gary Sent: Tuesday, February 12, 2002 9:38 AM To: Roensch, David; San-Juan-LaPlata, Team; Ingalls, Todd Cc: Graves, Jerry; Schoolcraft, Darrell; Asante, Ben Subject: La Plata Unit Fuel Valve Change-out Has there been an outage scheduled to replace the fuel valve on unit 2 at La Plata? Todd, where do we stand with the station control modifications?