RE: Outage Commercial Review Meeting (NNG, TW & NBPL)

From
Jerry Graves jerry.graves@enron.com
To
Jerry Graves, c..alexander@enron.com, Lynn Blair, mike.bonnstetter@enron.com, david.boothe@enron.com, jerry.boston@enron.com, Sharon Brown, Mike Bryant, John Buchanan, christopher.burns@enron.com, scott.clark@enron.com, Bill Cordes
and 63 more gary.corless@enron.com, Shelley Corman, Tracy Geaccone, Tom Gilbert, chuck.good@enron.com, Morgan Gottsponer, Charlie Graham, Steven Harris, Colleen Hood, randy.howard@enron.com, Steve January, Rich Jolly, fred.jordan@enron.com, John R. Keller, Terry Kowalke, Judy Kudym, Toby Kuehl, r..lawrence@enron.com, Randy LeBeau, Phil Lowry, Gary Maestas, greg.mall@enron.com, Donna Martens, rr.mcgillivray@enron.com, Jan Moore, Ronnie Morse, Mike Nelson, Dave Neubauer, Dave Odneal, Randy Rice, David Roensch, Darrell Schoolcraft, jim.schroeder@enron.com, Rick Smith, Gary Spraggins, LD Stephens, Steve Thomas, Kimberly Watson, Jo Williams, Walt Williams, Mansoor Abdmoulaie, Dennis Alters, Perry Frazier, Maurice Gilbert, Matt.Hughes@enron.com, Ron Matthews, gale.ramsaran@enron.com, Buzz Smith, ken.anderson@enron.com, doug.aschwege@enron.com, judy.beck@enron.com, carolyn.descoteaux@enron.com, dan.dobbins@enron.com, David L. Johnson, david.kolarik@enron.com, Bryan Reinecke, becki.sans@enron.com, roger.westfall@enron.com, Ben Asante, Gary Choquette, bob.mcchane@enron.com, John Sturn, errol.wirasinghe@enron.com
Date
Tue, 8 Jan 2002 12:09:59 -0800 (PST)
 The Stan Horton all employee meeting in Omaha is scheduled during the same time period as this meeting. If you are attending that meeting don't worry about getting to this one. Since we have very few outages to look at on the north end at this time, I'm going to keep to the schedule. If there are any questions or concerns please let me know.

Thank you
Jerry Graves
713-345-8923
Quoted or forwarded from earlier messages
-----Original Message-----
From: 	Graves, Jerry  
Sent:	Tuesday, January 08, 2002 1:42 PM
To:	Alexander, James C.; Blair, Lynn; Bonnstetter, Mike; Boothe, David; Boston, Jerry; Brown, Sharon; Bryant, Mike; Buchanan, John; Burns, Christopher; Clark, Scott; Cordes, Bill; Corless, Gary; Corman, Shelley; Geaccone, Tracy; Gilbert, Tom; Good, Chuck; Gottsponer, Morgan; Graham, Charlie; Graves, Jerry; Harris, Steven; Hood, Colleen; Howard, Randy; January, Steve; Jolly, Rich; Jordan, Fred; Keller, John R.; Kowalke, Terry; Kudym, Judy; Kuehl, Toby; Lawrence, James; Lebeau, Randy; Lowry, Phil; Maestas, Gary; Mall, Greg; Martens, Donna; McGillivray, RR; Moore, Jan; Morse, Ronnie; Nelson, Mike; Neubauer, Dave; Odneal, Dave; Rice, Randy; Roensch, David; Schoolcraft, Darrell; Schroeder, Jim; Smith, Rick; Spraggins, Gary; Stephens, LD; Thomas, Steve; Watson, Kimberly; Williams, Jo; Williams, Walt; Abdmoulaie, Mansoor; Alters, Dennis; Frazier, Perry; Gilbert, Maurice; Hughes, Matt; Matthews, Ron; Ramsaran, Gale; Smith, Buzz; Anderson, Ken; Aschwege, Doug; Beck, Judy; Descoteaux, Carolyn; Dobbins, Dan; Johnson, Robert L.; Kolarik, David; Reinecke, Bryan; Sans Souci, Becki; Westfall, Roger; Asante, Ben; Choquette, Gary; McChane, Bob; Sturn, John; Wirasinghe, Errol
Subject:	Outage Commercial Review Meeting  (NNG, TW & NBPL)


FYI,

The next Outage Coordination Commercial Review meeting is 01/09/02.  The purpose for the meeting is to discuss outages that have a flow impact for the month of February & March 2002. Please review the attached outage report. If you have any questions, please give me a call.  

Jerry Graves
713-345-8923 
                          << File: 010802Ts.XLS >>                                                   
When: January  9
Time:  1:00 to 2:00
Where: Houston 42C2
             Omaha  VCR - 6th floor
             Field - Conference # 877-795-3687  
                        Code # 755555




NORTHERN BORDER PIPELINE	
 	 	 	 	 	
 	Location	Date	Scope	Comments	
NB	CS13	01/10/02 to 01/10/02	Wash GG, and MP2.  (10 hrs)	Potential impact is low.	
NB	CS09	01/14/02 to 01/16/02	Unit Exchange, and emissions test.	Potential impact is low.	
NB	CS11	02/19/02 to 02/19/02	Wash GG, and MP2.  (10 hrs)	Potential impact is low.	
NB	CS12	03/05/02 to 03/05/02	Wash GG, and MP2.  (10 hrs)	Potential impact is low.