8 Jan 2002, 19:42 UTC
Outage Commercial Review Meeting (NNG, TW & NBPL)
- From
- Jerry Graves jerry.graves@enron.com
- To
-
c..alexander@enron.com, Lynn Blair, mike.bonnstetter@enron.com, david.boothe@enron.com, jerry.boston@enron.com, Sharon Brown, Mike Bryant, John Buchanan, christopher.burns@enron.com, scott.clark@enron.com, Bill Cordes, gary.corless@enron.com
and 63 more
Shelley Corman, Tracy Geaccone, Tom Gilbert, chuck.good@enron.com, Morgan Gottsponer, Charlie Graham, Jerry Graves, Steven Harris, Colleen Hood, randy.howard@enron.com, Steve January, Rich Jolly, fred.jordan@enron.com, John R. Keller, Terry Kowalke, Judy Kudym, Toby Kuehl, r..lawrence@enron.com, Randy LeBeau, Phil Lowry, Gary Maestas, greg.mall@enron.com, Donna Martens, rr.mcgillivray@enron.com, Jan Moore, Ronnie Morse, Mike Nelson, Dave Neubauer, Dave Odneal, Randy Rice, David Roensch, Darrell Schoolcraft, jim.schroeder@enron.com, Rick Smith, Gary Spraggins, LD Stephens, Steve Thomas, Kimberly Watson, Jo Williams, Walt Williams, Mansoor Abdmoulaie, Dennis Alters, Perry Frazier, Maurice Gilbert, Matt.Hughes@enron.com, Ron Matthews, gale.ramsaran@enron.com, Buzz Smith, ken.anderson@enron.com, doug.aschwege@enron.com, judy.beck@enron.com, carolyn.descoteaux@enron.com, dan.dobbins@enron.com, David L. Johnson, david.kolarik@enron.com, Bryan Reinecke, becki.sans@enron.com, roger.westfall@enron.com, Ben Asante, Gary Choquette, bob.mcchane@enron.com, John Sturn, errol.wirasinghe@enron.com - Date
- Tue, 8 Jan 2002 11:42:22 -0800 (PST)
FYI,
The next Outage Coordination Commercial Review meeting is 01/09/02. The purpose for the meeting is to discuss outages that have a flow impact for the month of February & March 2002. Please review the attached outage report. If you have any questions, please give me a call.
Jerry Graves
713-345-8923
When: January 9
Time: 1:00 to 2:00
Where: Houston 42C2
Omaha VCR - 6th floor
Field - Conference # 877-795-3687
Code # 755555
NORTHERN BORDER PIPELINE
Location Date Scope Comments
NB CS13 01/10/02 to 01/10/02 Wash GG, and MP2. (10 hrs) Potential impact is low.
NB CS09 01/14/02 to 01/16/02 Unit Exchange, and emissions test. Potential impact is low.
NB CS11 02/19/02 to 02/19/02 Wash GG, and MP2. (10 hrs) Potential impact is low.
NB CS12 03/05/02 to 03/05/02 Wash GG, and MP2. (10 hrs) Potential impact is low.