28 Sep 2001
Kevin Hyatt to Dennis Alters, Larry Campbell, Doug Cebryk and 9 more
No Sun Devil update meeting Monday 10/1
We expect the cost estimate to be completed 10/2 and will likely begin the weekly meeting Monday 10/8.
-
27 Sep 2001
Kimberly Watson to Mansoor Abdmoulaie, Morgan Gottsponer, Ron Matthews and 3 more
RE: TW/NNG & Sid Richardson
I've got it booked! Mark, please plan to attend with me. Thanks, Kim.
-
27 Sep 2001
Kimberly Watson to Stephen Herber, Mansoor Abdmoulaie and 4 more
RE: TW/NNG & Sid Richardson
I will be on vacation tomorrow through next week. I would be available pretty much anytime week of Oct. 8. Thanks, Kim.
-
27 Sep 2001
Mansoor Abdmoulaie to Kimberly Watson, Stephen Herber and 4 more
TW/NNG & Sid Richardson
Planning has met with ENA on Tuesday and responded to the questions from ENA. Let's four of us have a meeting in my office sometime next week and follow-up on this projec…
-
26 Sep 2001
Ron Matthews to Michelle Lokay, Dennis Alters
Sun DEvil Expansion Project
Attached is a spreadsheet showing capacities and costs by segments. The Phoenix lateral length has changed in scope and is a little longer. All of this will be included i…
-
26 Sep 2001
Audrey Robertson to Audrey Robertson, Mansoor Abdmoulaie, Ben Asante and 57 more
RE: ETS' TW Teams Appreciation Luncheon - Last Round
If you have not responded, please do so by today. Thanks, Audrey D. Robertson Transwestern Pipeline Company email address: audrey.robertson@enron.com (713) 853-5849 (713)…
-
26 Sep 2001
Maurice Gilbert to Kevin Hyatt and 6 more
RE: Salt storage
Kevin: Thanks for the information and 5000 feet of halite if it is one uniform bed is certainly similar to Gulf Coast salt domal opportunities. If you decide to move forw…
-
26 Sep 2001
Ron Matthews to Kimberly Watson and 2 more
Big Sandy Cost Estimate Modified
Attached is an Excel spreadsheet as before with an additional sheet totaling both the tie in and measurement.
-
25 Sep 2001
Michelle Lokay to Michelle Lokay, Steven Harris, Danny McCarty and 4 more
PG&E Strategy
Let's get together this Friday at 10:00 to discuss our strategy for next Tuesday's meeting with PG&E.
-
25 Sep 2001
Ron Matthews to Kimberly Watson, Dennis Alters, Morgan Gottsponer and 2 more
Caithness Big Sandy Project
Kim, The attached file contains a recap of the Timberline program results with a few mods. Basic information covers what Earl and I talked about today. Caithness engineer…
-
21 Sep 2001
Kimberly Watson to Ron Matthews
FW: Delivery Point Construction and Operations Agreement - Big Sandy
Ron, would you please give me your thoughts on Kirk's question. Thanks, Kim.
-
20 Sep 2001
Audrey Robertson to Dennis Alters, Ben Asante, Ramona Betancourt and 31 more
FW: New Location for Steve Harris' Staff Meeting
Please be informed, Steve Harris and the TW Commercial Group will temporarily relocated to the 13th floor effective Monday, September 24, 2001. Our present meeting locati…
-
20 Sep 2001
Kimberly Watson to Ketcherside, Kirk L (IGI Resources) and 2 more
Delivery Point Construction and Operations Agreement - Big Sandy
Kirk, Attached, please find the Delivery Point Construction and Operations Agreement. Please feel free to call me if you would like to walk through it. I would be availab…
-
20 Sep 2001
Ron Matthews to Doug Cebryk, Kevin Hyatt
RE: Panda Energy Extension
Doug, You're right!! Pipe size can swing the costs substantially. May be able to go down to a 20" or 24" depending on flow. Once I have a volume, I can size the line in a…
-
20 Sep 2001
Colleen Hood to Jesse Alvarado, Roy Armitage, team.artesia@enron.com and 69 more
Albuquerque Region Outage Reports Through May 2002
Please see attached report. Colleen Hood 402-398-7124
-
20 Sep 2001
Ron Matthews to Kimberly Watson, Lee Huber
Big Sandy Delivery Point Const and Oper Agreement
Attached shows a revision on page 2, paragraph 1.7. There are really two (2) 12" taps proposed; one tap on each the main and loop lines. They both swedge up immediately t…
-
19 Sep 2001
Kimberly Watson to Steven Harris, Teb Lokey, Lee Huber and 3 more
Big Sandy Delivery Point Const and Oper Agreement
Please review the attached agreement for the Big Sandy Interconnect. It is very standard. It is reimbursable. It has a few blanks that have to be filled in for certain da…
-
19 Sep 2001
Audrey Robertson to Audrey Robertson, Mansoor Abdmoulaie, Ben Asante and 55 more
Rescheduled Appreciation Luncheon for ETS' TW Teams
We are pleased to announce the new date and time of our Appreciation Luncheon. Please mark your calendars for Thursday, September 27, 11:30a - 3:00p. We will meet at the …
-
13 Sep 2001
Ron Matthews to Kimberly Watson and 2 more
Caithness - Big Sandy Project
As discussed earlier, the tap size for the above mentioned project is 16" and both main and loop lines would be tapped. The milepost for the tie in is MP116.5 right close…
-
12 Sep 2001
Darrell Schoolcraft to Lorraine Lindberg, Rich Jolly, Ron Matthews
RE: Gas temp
The gas temp that gas control see's leaving Roswell (station 9) is running between 85 to 95 degrees. Please if I'm looking at this wrong please correct me. Thanks DS
-
10 Sep 2001
Kevin Hyatt to Dennis Alters, Nancy Bagot, Larry Campbell and 26 more
Yahoo - Transwestern Pipeline Announces Successful Open Season for Proposed Sun
http://biz.yahoo.com/prnews/010910/dam046_1.html
-
10 Sep 2001
Jerry Graves to c..alexander@enron.com, Lynn Blair, mike.bonnstetter@enron.com and 77 more
Outage Coordination Commercial Review (Date Change)
FYI, Please take note of the date change. The next Outage Coordination Commercial Review meeting is 09/13/01. The purpose for the meeting is to discuss outages that have …
-
7 Sep 2001
Ron Matthews to Kevin Hyatt and 4 more
Ssun Devil Expansion Project - Level A Estimate
Attached is the scope and Level A cost estimate for the above mentioned project. This is the same package given to Engineering for them to prepare their Level B. Ron M.
-
5 Sep 2001
Bryan Reinecke to Kevin Hyatt, Ron Matthews
Revised Cost Estimate for El Paso Sun Devil Competitive Estimate
Kevin, Ron pointed out an error to me in my spreadsheet. The revised one is attached. The error was in the second case, high end cost estimate number (it was too low). It…