7 Jan 2002
Ron Matthews to marcello.minotti@enron.com, Arnold L. Eisenstein, Doug Cebryk and 2 more
Sun Devil Design Conditions
Sorry I left the above out of the first email. Attached is the latest and greatest taken from Winflow. There is a possibility of elimianting Bloomfield unit #5 but don't …
-
7 Jan 2002
Ron Matthews to Doug Cebryk, Arnold L. Eisenstein, Dennis Alters and 3 more
Sun Devil Alterative - Revision #10
Attached is a revised scope which basically includes the majority of the expansion volume to Phoenix. Only 30 MMcf/d goes west of Station #2 while 500 MMcf/d goes to Phoe…
-
26 Oct 2001
Ron Matthews to Steven Harris, Kimberly Watson, Lorraine Lindberg and 12 more
Mainline Expansion 250 & 300 MMcf/d Scenarios - Revised
The attached reflect Marketing's request to have interest, overheads, and AFUDC split out for all line items. The revision also includes recent additional input by Engine…
-
3 Oct 2001
Ron Matthews to John R. Keller, Jerry D. Martin, Doug Cebryk and 6 more
Sun Devil Cost Reconciliation
Attached is a Powerpoint slide showing the differences between the Planning's Level and Engineering's Level A+. Planning's Level A was update to include the current proje…
-
20 Sep 2001
Ron Matthews to Doug Cebryk, Kevin Hyatt
RE: Panda Energy Extension
Doug, You're right!! Pipe size can swing the costs substantially. May be able to go down to a 20" or 24" depending on flow. Once I have a volume, I can size the line in a…
-
30 Aug 2001
Ron Matthews to Norm Spalding, Morgan Gottsponer, John R. Keller and 7 more
RE: Sun Devil Pipeline Lengths
A preliminary model has been developed based on the limited information Doug, Kevin, and I discussed yesterday. A finished product won't be complete until such time as el…
-
22 Aug 2001
Ron Matthews to Kevin Hyatt, Morgan Gottsponer, Doug Cebryk and 4 more
Sun Devil Project - Level B Request "REVISED"
I found a mistake in the first Excel spreadsheet when discussing with Kim Kouri. Cost Estimate Summary sheet (2nd tab) did not add all of the rows down for the San Juan p…