Sun Devil Cost Reconciliation

From
Ron Matthews ron.matthews@enron.com
To
John R. Keller, Jerry D. Martin, Doug Cebryk, Arnold L. Eisenstein, Dennis Alters, Morgan Gottsponer, Kevin Hyatt, Eric Gadd, l..smith@enron.com
Date
Wed, 3 Oct 2001 09:10:31 -0700 (PDT)
Attached is a Powerpoint slide showing the differences between the Planning's Level and Engineering's Level A+.  Planning's Level A was update to include the current project scope uncovered through Engineering's investigation of the pipeline route and compressor stations.  Planning's estimated costs based on current facilities is around 21% of the Level A+ costs.  Normalizing the Level A brings the costs within 2% of the Engineering Level A+ estimate.