  1. 5 Apr 2001

    Mansoor Abdmoulaie to Lorraine Lindberg and 30 more

    TW-West Texas Expansion Level "A" release cost estimate 4/5/2001

    This is in response to your request of 3-26-2001 regarding the expansion of TW pipeline system in West Texas. Current Facility Capacity Summary Compression capacity at WT…

  2. 3 Apr 2001

    Mansoor Abdmoulaie to Kevin Hyatt and 8 more

    New Compressor Station in Eddy County, NM.

    As I mentioned the other day, one of the possible ways to receive high volume of gas from our customers is to design and construct new compression facilities adjacent to …

  3. 30 Mar 2001

    Jeffery Fawcett to Kirk Ketcherside and 16 more

    Big Sandy Project

    Kirk, Great to hear that the project is moving forward. I think TW feels it's emotionally vested at this point! I will ask the Facility Planning folks to get started on p…

  4. 27 Mar 2001

    Mansoor Abdmoulaie to Lorraine Lindberg and 6 more

    TW/ BP in Eddy County, NM.

    This is a level "A" cost estimate (?30%) to tie BP's gas to TW high-pressure line in Eddy County NM. A) 30 mmcf/d case (BP pressure=1000 psig): 13 miles of 10" (OD) pipel…

  5. 26 Mar 2001

    Eugene O'Gorman to Arnold L Eisenstein and 12 more

    RE: Nitrogen facility

    I quickly reviewed the Engelhard technology. It may have some nice applications. Here are the issues with this nitrogen rejection technology. Adaptation of PSA technology…

  6. 23 Mar 2001

    Kevin Hyatt to Lindy Donoho, Jeffery Fawcett, Lorraine Lindberg and 9 more

    FW: Cost Estimate

    TEAM- Below is a project request spreadsheet developed by Facility Planning. We will use this form in an attempt to better communicate and track ALL the various cost esti…

  7. 23 Mar 2001

    Donna Martens to Mary Kay Miller, Phil Lowry, Keith Petersen and 27 more

    Final Red Rock

    Attached is the final document with attachments for the Red Rock filing. Please let me know by 3 P.M. on Friday (3/23) if you have any comments or concerns. Also, please …

  8. 15 Mar 2001

    Arnold Eisenstein to Jerry D. Martin and 30 more

    Red Rock Weekly Report

    1. ACTIVITIES: A. Discussions with TW on critical items in order to finalize FERC application: Navajo Environmental has requested a Threatened & Endangered Species (T&E) …

  9. 15 Mar 2001

    Kevin Hyatt to Lorraine Lindberg, Eric Faucheaux and 6 more

    RE: Cost Estimate

    I thought we agreed all project requests would be submitted in writing to Facility Planning on the Project Sheet we developed. The Sheet is important in that it highlight…

  10. 13 Mar 2001

    Perry Frazier to Michelle Lokay and 6 more

    P-2 Coolers and recycle line.

    I understand this Level A is approved for work order generation. This is the cost from FP for a recyle line and coolers at P-2 to handle NNG Gray flows to Station # 9. Th…

  11. 13 Mar 2001

    Michelle Lokay to Earl Chanley and 12 more

    RE: Pogo Interconnect

    After many conversations with John Havard at Pogo, it was decided that we will not continue with the Transwestern interconnect in the Pronghorn area. The drilling results…

  12. 12 Mar 2001

    Donna Martens to Arnold L Eisenstein, Earl Chanley, Larry Campbell and 32 more

    Red Rock issues

    The following issues need to be addressed for the filing: In regard to the trees within the station yard at Station 2 --- are we correct in saying we will be on "previous…

  13. 12 Mar 2001

    Rich Jolly to Mike McCracken and 8 more

    Re: Red Cedar La Plata

    Thanks Mike let me know what we can do to assist you in this. RJ Mike McCracken 03/09/2001 04:20 PM To: Kevin Hyatt/ET&S/Enron, Lorraine Lindberg/ET&S/Enron, Eric Fauchea…

  14. 10 Mar 2001

    Arnold Eisenstein to Jerry D. Martin and 30 more

    Red Rock Weekly Report

    1. ACTIVITIES: a. Completed site visit to all stations and evaluation of existing facilities b. Discussions with TW on critical items in order to finalize FERC applicatio…

  15. 8 Mar 2001

    Lorraine Lindberg to Perry Frazier and 18 more

    RE: EPFS interconnect

    I need as close to the exact cost for both 65,000 and 90,000 MMBtu/d as we can get. EPFS is going to pay for this and I don't want ETS to fund anything so it's important …

  16. 8 Mar 2001

    Perry Frazier to Lorraine Lindberg and 18 more

    RE: EPFS interconnect

    Let me know if you need a level A or level B, in my book a level B is a "good to go" estimate. The prior scope of 60 MMBtu/d was the max. the tap could handle, any thing …

  17. 7 Mar 2001

    Jeffery Fawcett to Ben Asante, Eric Faucheaux and 6 more

    Topock Lateral

    Gentlemen, In addition to looking for ways in which Transwestern can improve mainline deliverability, another important criteria is access to markets. With the addition o…

  18. 7 Mar 2001

    Lorraine Lindberg to Perry Frazier, Arnie Bailey and 16 more

    RE: EPFS interconnect

    I just got off the phone with El Paso Field Services. At this time, I now need 2 cost estimates. One to increase the facilities to be able to handle up to 65,000 MMBtu/d …

  19. 6 Mar 2001

    Mike McCracken to Kevin Hyatt, Michelle Lokay, Jeffery Fawcett and 34 more

    Marketing Roundtable Notes

    All Thank you very much for the great attendance and participation! Thanks, also, to all those who had to juggle this meeting with others. Attached are the notes from the…

  20. 5 Mar 2001

    Lorraine Lindberg to Eric Faucheaux and 2 more

    EPFS interconnect

    Eric - Please provide me with a cost estimate to increase the meter facilities from 40,000 MMBtu/d to 60,000 MMBtu/d at the new receipt point with El Paso Field Services …

  21. 3 Mar 2001

    Donna Martens to Rich Jolly, Arnold L Eisenstein, David Roensch and 22 more

    Red Rock Expansion

    Please review attached redline draft and provide comments and the signed FERC approval form by 2 P.M. on Tuesday, March 6. Questions, let me know. Thanks. Donna

  22. 2 Mar 2001

    Ben Asante to Gary Choquette and 30 more

    Re: Needles Pressure Requirement

    Great Gary, Can you please do something quick to tell us what the Needles pressure need to be? Thx

  23. 2 Mar 2001

    Gary Choquette to Kenneth Chow, bob.mcchane@enron.com, Kim Kouri and 12 more

    Needles Pressure Requirement

    I've got a copy of the SoCal contract for Needles. The exact wording for the pressure requirement is: SECTION 5. PRESSURE. Seller shall tender gas to Buyer, at the delive…

  24. 24 Feb 2001

    Donna Martens to Rich Jolly, Arnold L Eisenstein, David Roensch and 24 more

    Red Rock Expansion Filing

    Attached is a draft copy of Transwestern's application requesting authorization to abandon the existing units at Stations 1, 2, 3 and 4 and install a 38,000 HP unit at ea…

  25. 23 Feb 2001

    Rich Jolly to Mike McCracken and 12 more

    Re: Agave & Atoka System