15 Mar 2001, 01:04 UTC
RE: Cost Estimate
- From
- Kevin Hyatt kevin.hyatt@enron.com
- Date
- Wed, 14 Mar 2001 17:04:18 -0800 (PST)
I thought we agreed all project requests would be submitted in writing to Facility Planning on the Project Sheet we developed. The Sheet is important in that it highlights certain requirements for a particular project (including due date, contact names, phone numbers, etc.). You can fill out the sheet on-line and attach it as an email to Eric. Let me know if you have questions/concerns. thanks kh
Quoted or forwarded from earlier messages
-----Original Message----- From: Lindberg, Lorraine Sent: Mon 3/12/2001 9:26 AM To: Faucheaux, Eric Cc: Hyatt, Kevin Subject: Cost Estimate Eric - Could you please provide me with a Level A cost estimate to make the Ft. Wingate delivery point in McKinley County, NM a bi-directional point? PNM would like to deliver up to 15,000 MMBtu/d to TW if the price is right. Thank you. Lorraine