20 Sep 2001
Ron Matthews to Doug Cebryk, Kevin Hyatt
RE: Panda Energy Extension
Doug, You're right!! Pipe size can swing the costs substantially. May be able to go down to a 20" or 24" depending on flow. Once I have a volume, I can size the line in a…
-
20 Sep 2001
Ron Matthews to Kimberly Watson, Lee Huber
Big Sandy Delivery Point Const and Oper Agreement
Attached shows a revision on page 2, paragraph 1.7. There are really two (2) 12" taps proposed; one tap on each the main and loop lines. They both swedge up immediately t…
-
13 Sep 2001
Ron Matthews to Kimberly Watson and 2 more
Caithness - Big Sandy Project
As discussed earlier, the tap size for the above mentioned project is 16" and both main and loop lines would be tapped. The milepost for the tie in is MP116.5 right close…
-
7 Sep 2001
Ron Matthews to Kevin Hyatt and 4 more
Ssun Devil Expansion Project - Level A Estimate
Attached is the scope and Level A cost estimate for the above mentioned project. This is the same package given to Engineering for them to prepare their Level B. Ron M.
-
30 Aug 2001
Ron Matthews to Norm Spalding, Morgan Gottsponer, John R. Keller and 7 more
RE: Sun Devil Pipeline Lengths
A preliminary model has been developed based on the limited information Doug, Kevin, and I discussed yesterday. A finished product won't be complete until such time as el…
-
22 Aug 2001
Ron Matthews to Kevin Hyatt, Morgan Gottsponer, Doug Cebryk and 4 more
Sun Devil Project - Level B Request "REVISED"
I found a mistake in the first Excel spreadsheet when discussing with Kim Kouri. Cost Estimate Summary sheet (2nd tab) did not add all of the rows down for the San Juan p…
-
21 Aug 2001
Ron Matthews to Kevin Hyatt, Morgan Gottsponer and 2 more
Sun Devil Project - Level B Request
Attached is a Level B request for the Sun Devil project. Keep in mind that this should include only right of way at this time. Details on the compression will probably ch…
-
20 Aug 2001
Ron Matthews to Kevin Hyatt, Morgan Gottsponer, Eric Faucheaux
Sun Devil Project
Attached is the latest and greatest breakdown of facilities and Level A costs related to Sun Devil. Facilities are not final and will be refined as the project unfolds.
-
13 Aug 2001
Ron Matthews to ketchek@bp.com and 6 more
Caithness - Big Sandy Project
Attached are the engineering standards you requested on our latest telephone discussion with Kim Watson. Also attached is a cost estimate summary that the numbers were ma…