7 Aug 2001, 22:35 UTC
RE: Outage Coordination Commercial Review
- From
- Kimberly Watson kimberly.watson@enron.com
- To
- Jerry Graves
- Date
- Tue, 7 Aug 2001 15:35:11 -0700 (PDT)
Jerry, Unfortunately, our marketing department is off campus tomorrow with are Facility Planning group and will be unable to attend. We will catch you next month. Thanks, Kim.
Quoted or forwarded from earlier messages
-----Original Message-----
From: Graves, Jerry
Sent: Tuesday, August 07, 2001 3:43 PM
To: Alexander, James C.; Bellard, Dannis; Blair, Lynn; Bonnstetter, Mike; Boothe, David; Boston, Jerry; Brown, Sharon; Bryant, Mike; Buchanan, John; Burns, Christopher; Clark, Scott; Cordes, Bill; Corless, Gary; Corman, Shelley; Geaccone, Tracy; Gilbert, Tom; Good, Chuck; Gottsponer, Morgan; Graham, Charlie; Graves, Jerry; Harris, Steven; Hood, Colleen; Howard, Randy; Howell, Dennis; January, Steven; Jolly, Rich; Jordan, Fred; Keller, John R.; Kowalke, Terry; Kudym, Judy; Kuehl, Toby; Lawrence, James; LeBeau, Randy; Lowry, Phil; Maestas, Gary; Mall, Greg; McGillivray, RR; Mertz, Tom; Moore, Jan; Morse, Ronnie; Nelson, Michel; Odneal, Dave; Pribble, Dan; Rice, Randy; Roensch, David; Schoolcraft, Darrell; Schroeder, Jim; Smith, Rick; Spraggins, Gary; Stephens, LD; Swett, Larry; Sztroin, David; Teal, Mike; Thomas, Steve; Thompson, Charlie; Watson, Kimberly; Weatherford, Allan; Williams, Jo; Williams, Walt; Abdmoulaie, Mansoor; Alters, Dennis; Dushinske, Adam; Faucheaux, Eric; Frazier, Perry; Gilbert, Maurice; Hughes, Matt; Matthews, Ronald; Ramsaran, Gale; Smith, Buzz; Anderson, Ken; Aschwege, Doug; Beck, Judy; Descoteaux, Carolyn; Dobbins, Dan; Johnson, Robert L.; Kolarik, David; Reinecke, Bryan; Sans Souci, Becki; Westfall, Roger; Asante, Ben; Choquette, Gary; Kouri, Kim; McChane, Bob; Sturn, John; Wirasinghe, Errol
Subject: Outage Coordination Commercial Review
FYI,
8/08/01, is the next Outage Coordination Commercial Review meeting. There will be a few changes to the monthly meeting. First, you will see the name has changed. The change was made to help maintain our focus of the meeting. Which is review the outages where flows are affected and discuss their impact with the Commercial groups. The meeting will focus mainly on outages that have some throughput loss. If you have any questions or concerns please give me a call.
Thank you
Jerry Graves
713-345-8923
<< File: 080701CR.xls >>
When: August 8
Time: 1:00 to 2:00
Where: Houston 49C2
Omaha VCR - 7th floor
Field Personnel - Conference # 877-795-3687
Code # 755555
Northern Border Pipeline
Location Date Scope Comments
CS05 08/16/01 to 08/16/01 MP2, Scope, GG swap, and replace wire from main breaker to auxiliary. (14 hrs.) (Potential impact is low)
CS13 08/09/01 to 08/09/01 Bore scope inspection, wash, MP2, and install M/L Block Valve mods. (8hrs.) (Potential impact is low)
CS06 08/21/01 to 08/21/01 Borescope inspection, wash, MP2, and replace engine starter with modified starter. (10 hrs.) (Potential impact is low)
CS11 08/28/01 to 08/28/01 Scope, Wash, MP2 /L Block Valve addition, (10 hrs) (Potential impact is low)
CS02 09/05/01 to 09/05/01 Scope, Wash, MP2 (10 hrs) (Potential impact is low)
CS04 09/11/01 to 09/11/01 Scope, MP2, Emissions testing. (10 hrs) (Potential impact is low)
CS07 09/18/01 to 09/18/01 Scope, Wash, MP2, and replace Argotech pump. (10 hrs) (Potential impact is low)
CS09 09/25/01 to 09/25/01 Scope, MP2, Clean oil coolers. (10 hrs) (Potential impact is low)