Enron email

Algorithmic Indexing

9 Aug 2001, 14:46 UTC

RE: Outage Coordination Commercial Review

From
Kimberly Watson kimberly.watson@enron.com
To
Jerry Graves
Date
Thu, 9 Aug 2001 07:46:59 -0700 (PDT)
Thanks for the future dates.  I'll try not to schedule any more conflicts with this time......    :>).    Kim.
Quoted or forwarded from earlier messages
-----Original Message-----
From: 	Graves, Jerry  
Sent:	Wednesday, August 08, 2001 7:06 AM
To:	Watson, Kimberly
Subject:	RE: Outage Coordination Commercial Review


Ouch!!   
Thanks for letting me know Kim. Here are the planned dates for the Commercial Review for the rest of the year. Keep in mind that the dates can be changed. The time and the place are the same. I would have to say, that I am crushed. Picking those Planning guys over the Outage CoordinatorJ Their not cool?

See you next time

Jerry

Sept.  12th
Oct.   11th
Nov.  14th
Dec.  11th


 -----Original Message-----
From: 	Watson, Kimberly  
Sent:	Tuesday, August 07, 2001 5:35 PM
To:	Graves, Jerry
Subject:	RE: Outage Coordination Commercial Review

Jerry,

Unfortunately, our marketing department is off campus tomorrow with are Facility Planning group and will be unable to attend.  We will catch you next month. 

Thanks, Kim. 

 -----Original Message-----
From: 	Graves, Jerry  
Sent:	Tuesday, August 07, 2001 3:43 PM
To:	Alexander, James C.; Bellard, Dannis; Blair, Lynn; Bonnstetter, Mike; Boothe, David; Boston, Jerry; Brown, Sharon; Bryant, Mike; Buchanan, John; Burns, Christopher; Clark, Scott; Cordes, Bill; Corless, Gary; Corman, Shelley; Geaccone, Tracy; Gilbert, Tom; Good, Chuck; Gottsponer, Morgan; Graham, Charlie; Graves, Jerry; Harris, Steven; Hood, Colleen; Howard, Randy; Howell, Dennis; January, Steven; Jolly, Rich; Jordan, Fred; Keller, John R.; Kowalke, Terry; Kudym, Judy; Kuehl, Toby; Lawrence, James; LeBeau, Randy; Lowry, Phil; Maestas, Gary; Mall, Greg; McGillivray, RR; Mertz, Tom; Moore, Jan; Morse, Ronnie; Nelson, Michel; Odneal, Dave; Pribble, Dan; Rice, Randy; Roensch, David; Schoolcraft, Darrell; Schroeder, Jim; Smith, Rick; Spraggins, Gary; Stephens, LD; Swett, Larry; Sztroin, David; Teal, Mike; Thomas, Steve; Thompson, Charlie; Watson, Kimberly; Weatherford, Allan; Williams, Jo; Williams, Walt; Abdmoulaie, Mansoor; Alters, Dennis; Dushinske, Adam; Faucheaux, Eric; Frazier, Perry; Gilbert, Maurice; Hughes, Matt; Matthews, Ronald; Ramsaran, Gale; Smith, Buzz; Anderson, Ken; Aschwege, Doug; Beck, Judy; Descoteaux, Carolyn; Dobbins, Dan; Johnson, Robert L.; Kolarik, David; Reinecke, Bryan; Sans Souci, Becki; Westfall, Roger; Asante, Ben; Choquette, Gary; Kouri, Kim; McChane, Bob; Sturn, John; Wirasinghe, Errol
Subject:	Outage Coordination Commercial Review



FYI,

 8/08/01, is the next Outage Coordination Commercial Review meeting.  There will be a few changes to the monthly meeting. First, you will see the name has changed. The change was made to help maintain our focus of the meeting. Which is review the outages where flows are affected and discuss their impact with the Commercial groups. The meeting will focus mainly on outages that have some throughput loss. If you have any questions or concerns please give me a call.  

Thank you

Jerry Graves 
713-345-8923
                                                                                       << File: 080701CR.xls >> 

When: August 8
Time: 1:00 to 2:00
Where: Houston 49C2
             Omaha  VCR - 7th floor
             Field Personnel - Conference # 877-795-3687  
                                         Code # 755555


Northern Border Pipeline
 Location	Date  	Scope 	Comments	
				
CS05	08/16/01 to 08/16/01	MP2, Scope, GG swap, and replace wire from main breaker to auxiliary.  (14 hrs.)	(Potential impact is low)	
CS13	08/09/01 to 08/09/01	Bore scope inspection, wash, MP2, and install M/L Block Valve mods. (8hrs.)	(Potential impact is low)	
CS06	08/21/01 to 08/21/01	Borescope inspection, wash, MP2, and replace engine starter with modified starter. (10 hrs.)	(Potential impact is low)	
CS11	08/28/01 to 08/28/01	Scope, Wash, MP2 /L Block Valve addition, (10 hrs)	(Potential impact is low)	
CS02	09/05/01 to 09/05/01	Scope, Wash, MP2  (10 hrs)	(Potential impact is low)	
CS04	09/11/01 to 09/11/01	Scope, MP2, Emissions testing. (10 hrs)	(Potential impact is low)	
CS07	09/18/01 to 09/18/01	Scope, Wash, MP2, and replace Argotech pump. (10 hrs)	(Potential impact is low)	
CS09	09/25/01 to 09/25/01	Scope, MP2, Clean oil coolers. (10 hrs)	(Potential impact is low)