12 Feb 2002, 23:16 UTC
Station 8 Unloader Installation
- From
- Mike McCracken mike.mccracken@enron.com
- Date
- Tue, 12 Feb 2002 15:16:16 -0800 (PST)
Darrell / Jerry We are about ready to install the unloader system at Station 8 to wrap up the automation project. We've been working on installing electrical and mechanical equipment without disabling the units. The valve people estimate 2 days per unit to install the valve actuators / unloaders and do some commissioning work. We just need one unit at a time. Do we need to wait until the tarriff months are over? Jerry can you send me an outage request form? Thanks Mike