13 Feb 2002, 14:21 UTC
RE: Station 8 Unloader Installation
- From
- Darrell Schoolcraft darrell.schoolcraft@enron.com
- Date
- Wed, 13 Feb 2002 06:21:26 -0800 (PST)
Just let gas control know what units you are going to have unavailable. You can proceed with the project. ds
Quoted or forwarded from earlier messages
-----Original Message-----
From: Graves, Jerry
Sent: Wednesday, February 13, 2002 7:00 AM
To: McCracken, Mike; Schoolcraft, Darrell
Subject: RE: Station 8 Unloader Installation
Mike, I think we can go ahead and do the work. There is no flow affect right now, so I don't see a problem doing one unit at a time. Darrell what's your thoughts?
Here is a blank outage request form Mike.
Jerry
<< File: Outage Form2.doc >>
-----Original Message-----
From: McCracken, Mike
Sent: Tuesday, February 12, 2002 5:16 PM
To: Graves, Jerry; Schoolcraft, Darrell
Subject: Station 8 Unloader Installation
Darrell / Jerry
We are about ready to install the unloader system at Station 8 to wrap up the automation project. We've been working on installing electrical and mechanical equipment without disabling the units. The valve people estimate 2 days per unit to install the valve actuators / unloaders and do some commissioning work. We just need one unit at a time.
Do we need to wait until the tarriff months are over? Jerry can you send me an outage request form?
Thanks
Mike