RE: FW: Transmission curtailments - PG&E Proposal

From
Ress Young ress.young@enron.com
To
Jeff Nieland
Cc
Jeff Dasovich, John Wack, Jess Galura, Roger Yang, Tom Riley, Chris Holmes
Bcc
Jeff Dasovich, John Wack, Jess Galura, Roger Yang, Tom Riley, Chris Holmes
Date
Wed, 27 Sep 2000 06:50:00 -0700 (PDT)
Jeff,
This is really a grid reliability program directed by the CA ISO under stage 
3 emengency, it is therefore not dependent on whether the customer is 
receiving "energy" product from PG&E the utility or other ESPs since everyone 
is a user of the grid for transmission services.  My understanding is that 
the only way to avoid curtailments is to get certified by CPUC as "essential" 
end-user.  I think recently the BART train system successfully lobbied the 
CPUC to certify it as essential.  Of course it will be a tough sell to do the 
same for a private enterprise.  Realistically the only way to cover such 
non-econcomic driven interruption is to put in on site back up generation.  

Ress