with:stephanie.miller@enron.com means Stephanie Miller (stephanie.miller@enron.com).
-
29 Sep 2000
Stephanie Miller to Jeff Dasovich
lost e:mail
I noticed an e:mail from you that I inadvertantly deleted. Can you please send it again? Sue has volunteered to send info on NP15....appreciate your help. Thanks! Stephan…
-
28 Sep 2000
Jeff Dasovich to Stephanie Miller
(no subject)
Hi. Did you hear from Sue Mara re: how the California ISO works?
-
21 Sep 2000
John Hodge to Julie A Gomez, Scott Neal, Brad McKay and 6 more
MarketLink Shippers
Additional information on the Transco MarketLink shippers: Shipper Phase Volume Term Delivery Pt Rate Aquila I 25,000 Dthd 10 years Manhattan $0.35 Consolidated Edison I …
-
21 Sep 2000
John Hodge to Julie A Gomez, Scott Neal, Brad McKay and 4 more
MarketLink Shippers
Transco filed service agreements with the FERC for MarketLink (Leidy - Zone 6) yesterday. The project will start in two phases. The shippers and phases are as follows: Ph…
-
8 Sep 2000
Ruth Concannon to Janet Dietrich and 8 more
Keyspan Asset Management Deal True-up
Janet, Colleen Sullivan has replaced Kate Fraser in the team to finalize the negotiations with the folks at Keyspan. My intention is to finish up the calculations that Co…
-
7 Sep 2000
Ruth Concannon to Jeff Dasovich and 2 more
Draft CEC Testimony for Pastoria Plant
Jeff -- Stephanie Miller asked me to send you this draft testimony that our group put together. Allan Thompson and Sam Wehn are looking it over now. The map is not quite …
-
6 Sep 2000
Jeff Dasovich to Chris H Foster, Julie A Gomez, Timothy J Hamilton and 2 more
GIR: FELLOW SIGNATORIES TO THE COMPREHENSIVE SETTLEMENT - ALTRA
FYI. Under the settlement with SoCal, PG&E and countless others, Altra was going to provide the platform for the (unregulated) secondary markets in intrastate storage, ca…
-
6 Sep 2000
Mathew Gimble to David Fairley, Ozzie Pagan, Rusty Stevens and 32 more
Updated Timetable
Attached is an updated Timetable detailing the critical path issues of the Fort Pierce Repowering Project. Specifically, note items scheduled for completion during the ne…