6 Sep 2000, 10:27 UTC
Updated Timetable
- From
- Mathew Gimble mathew.gimble@enron.com
- To
-
David Fairley, Ozzie Pagan, Rusty Stevens, Kevin M Presto, Rogers Herndon, Edward Baughman, berney.aucoin@enron.com, Gautam Gupta, Stephanie Miller, John Hodge, Scott Neal, Jared Kaiser
and 23 more
Sandra F Brawner, Ed McMichael Jr., John Griffith, Sheila Tweed, Barton Clark, Bruce Golden, Mike Coleman, Darrell Stovall, Richard Bickings, walter.coffer@enron.com, Lisa Bills, Sarah Wesner, Herman Manis, Roseann Engeldorf, Jody Pierce, Chip Schneider, David Marshall, Patrick Maloy, ted.ryan@enron.com, Dave Kellermeyer, George McCormick, Webb Jennings, karen.carter@enron.com - Date
- Wed, 6 Sep 2000 03:27:00 -0700 (PDT)
Attached is an updated Timetable detailing the critical path issues of the Fort Pierce Repowering Project. Specifically, note items scheduled for completion during the next two weeks, such as: Internal/External review and execution of the Land Lease Option, Ground Lease and Project Development Agreement Preparation of an EPC contract Site visit to an existing, enclosed 7FA and HRSG (Coyote Springs appears to be the best option) Review and prepare applications for an air permit, an ERP (if necessary), special use permit, waste water permit and interconnect request Let me know of ANY conflicts, concerns or adjustments associated with the attached. Thanks again for your help, Mathew