27 Sep 2000
Fred Mitro to Kay Mann and 4 more
Pontiac Site - Interconnection Feasibility Study
Kay Attached is a proposal from ComEd to complete an Interconnect Feasibility Study(IFS) on the Pontiac project site. I believe that the form of this agreement is consist…
-
25 Sep 2000
Kay Mann to Matthew F Gockerman, Rusty Stevens, Fred Mitro
Enron - Livingston County PRIVILEGED AND CONFIDENTIAL
Matt, Since so much of this related to tax, I thought you should have a look at it. Rusty/Fred, I'm not sure of the context of the presentation of the information. Is thi…
-
25 Sep 2000
Kay Mann to Karen S. - CHI Way and 4 more
Re: livingston county proposed conditions to special use
Karen, Could we have the option of using a letter of credit versus a corporate guaranty? (8) "Way, Karen S. - CHI" <karen.way@piperrudnick.com> on 09/21/2000 05:15:36 PM …
-
25 Sep 2000
-
21 Sep 2000
Karen S. - CHI Way to Rusty Stevens, Fred Mitro, Kay Mann and 2 more
livingston county proposed conditions to special use
Following are the proposed conditions to special use which we will be submitting to the County for their review and attachment to the final zoning approvals. Please revie…
-
21 Sep 2000
Fred Mitro to Karen S. - CHI Way and 6 more
Re: livingston county proposed conditions to special use
See my comments [in red] below. Fred "Way, Karen S. - CHI" <karen.way@piperrudnick.com> on 09/21/2000 05:15:36 PM To: "'rusty.stevens@enron.com'" <rusty.stevens@enron.com…
-
20 Sep 2000
Re: ledford-titan option to purchase , livingston county.DOC
No problem. I got some comments from Accounting, but I'm fine if you want it to go out with the caveat that Enron has a couple of minor administrative points to clear up.…
-
20 Sep 2000
Re: ledford-titan option to purchase , livingston county.DOC
Thanks Kay. Enron North America Corp. From: Kay Mann 09/20/2000 08:52 AM To: "Way, Karen S. - CHI" <karen.way@piperrudnick.com> cc: Rusty Stevens/Corp/Enron@ENRON, Fred M…
-
20 Sep 2000
Kay Mann to Karen S. - CHI Way and 8 more
Re: ledford-titan option to purchase , livingston county.DOC
Here are my comments: Revise "whereas" clauses to make it an option for an easement, not a current grant of an easement. Should we be able to enter all of Parcel 2 for du…
-
19 Sep 2000
Kay Mann to Karen S. - CHI Way and 2 more
RE: Fehr Option Agreement
Hi Karen, Our accounting contact is leaving tomorrow at 100, so it would be helpful to get this information as soon as possible. It would also help if you could send a re…
-
18 Sep 2000
Re: Fehr Option Agreement
As soon as I get a redline, I'll get it to Accounting and we can go forward quickly. I will also process the Virgil and Joan Ledford deal at the same time. I just had a m…
-
18 Sep 2000
Karen S. - CHI Way to Kay Mann, Rusty Stevens, Fred Mitro and 4 more
RE: Fehr Option Agreement
I spoke to Don Shindler about your comments. We will hold the contract and any discussions with the Seller's attorney pending your approval following discussions with you…
-
18 Sep 2000
Karen S. - CHI Way to Kay Mann, Rusty Stevens, Fred Mitro and 4 more
Option to Purchase Real Estate re TitanFehr.DOC
<<Option to Purchase Real Estate re TitanFehr.DOC>> Kay: Per your previous email, attached is the electronic version of the Titan-Fehr Option for your review. Please call…
-
18 Sep 2000
Kay Mann to Rusty Stevens and 4 more
Re: Fehr Option Agreement
Here are my observations: I agree with Rusty re: the put option complicating things for us. Second, there has to be an absolute end to this agreement at some point. If we…
-
15 Sep 2000
Karen S. - CHI Way to Kay Mann, Fred Mitro, Rusty Stevens and 2 more
ledford-titan option to purchase , livingston county.DOC
<<ledford-titan option to purchase , livingston county.DOC>> Attached hereto, please find the draft Ledford-Titan Option to Purchase Real Estate and Grant of Easement for…
-
14 Sep 2000
Rusty Stevens to Karen S. - CHI Way, Kay Mann and 2 more
Fehr Option Agreement
I am in receipt of the Fehr's comments to our option agreement. In reviewing them, I have the following comments: The paragraph (2) change that says they can compel us to…
-
13 Sep 2000
Fred Mitro to Scott Healy, Rusty Stevens, Stephen Plauche and 4 more
WEPCO Term Sheet - Plano
Attached is a copy of the term sheet which I faxed to WEPCO on Monday afternoon of this week. This proposal utilized the ComEd term sheet as a template and was modified b…
-
6 Sep 2000
Mathew Gimble to David Fairley, Ozzie Pagan, Rusty Stevens and 32 more
Updated Timetable
Attached is an updated Timetable detailing the critical path issues of the Fort Pierce Repowering Project. Specifically, note items scheduled for completion during the ne…
-
1 Sep 2000
Fred Mitro to Scott Healy, Rusty Stevens, Stephen Plauche and 5 more
ComEd Term Sheet - Plano
Attached are the clean and red-line versions of the ComEd Tolling term sheet on the Plano site. I will fax the clean version to ComEd's wholesale group this afternoon. I …
-
1 Sep 2000