with:perry.frazier@enron.com means Perry Frazier (perry.frazier@enron.com).
-
24 Apr 2001
Steven Harris to Mary Kay Miller and 20 more
Re: TW 10 year capacity posting
Mary Kay, although we did want to post for 10 years because it helped us in negotiating future contracts, it is no longer necessary to do so for such an extended period. …
-
20 Apr 2001
Lindy Donoho to lee.dennis@enron.com, Jeffery Fawcett, Perry Frazier and 5 more
Updated ROFR List
Please see attached which includes: Mavrix Amd 14,000/d in 2003 E to W Duke 20,000/d E to E NNS 1,300/d W to W Richardson 2,000/d E to E
-
20 Apr 2001
Michelle Lokay to Martha Cormier and 4 more
Mavrix ROFR
For the Mavrix contract ending 10/31/2003...do not give Right of First Refusal. Thanks!
-
19 Apr 2001
Karen Brostad to Linda Trevino, Perry Frazier, james.moore@enron.com and 24 more
New PNR points on Transwestern
Per request from Marketing I have established the following new Park and Ride points for Transwestern Pipeline. These points have been added to the PNR template in CBS, a…
-
12 Apr 2001
Dennis Lee to Susan M Scott and 12 more
RE: Transwestern Contracting Issues
I'm sorry...9:00 AM DL From: Susan Scott/ENRON@enronXgate on 04/12/2001 09:34 AM To: Dennis Lee/ET&S/Enron@ENRON, Kevin Hyatt/ENRON@enronxgate, Elizabeth Brown/ET&S/Enron…
-
10 Apr 2001
Mansoor Abdmoulaie to Kevin Hyatt and 8 more
TW/ Agave---Atoka-3 capacity
This is in response to our meeting of April-10-2001 in Midland with Agave. Assuming units #761 and #762 are now assigned to LEC-10" service, the below schematic is showin…
-
5 Apr 2001
Mansoor Abdmoulaie to Lorraine Lindberg and 30 more
TW-West Texas Expansion Level "A" release cost estimate 4/5/2001
This is in response to your request of 3-26-2001 regarding the expansion of TW pipeline system in West Texas. Current Facility Capacity Summary Compression capacity at WT…
-
4 Apr 2001
Eric Faucheaux to Lorraine Lindberg, Bob Burleson and 18 more
EPFS Cost Estimate
With reference to our meeting that we had on Monday morning (4/2) regarding competing suppliers for capacity on the Crawford Lateral (Duke and EPFS), Planning has determi…
-
3 Apr 2001
Dennis Lee to Nancy Bastida, zuela.carter@enron.com, Martha Cormier and 13 more
Capacity Requests for TW
Effective immediately, the contracts group will change the procedure for capacity requests for Transwestern. A note will continue to be sent via Lotus Notes showing the r…
-
3 Apr 2001
Mansoor Abdmoulaie to Kevin Hyatt and 8 more
New Compressor Station in Eddy County, NM.
As I mentioned the other day, one of the possible ways to receive high volume of gas from our customers is to design and construct new compression facilities adjacent to …