with:mark.walker@enron.com means Mark V Walker (mark.walker@enron.com).
-
31 May 2002
Jeff Duff to Mark V Walker, Mark Fisher
FAULTS CLOCK field
While we await this infromation to be added to STAR here is a spread sheet with the clock acronyms. It may be helpful to pull into Splus as a dataframe from use? JD
-
31 May 2002
Mark V Walker to Kurt Anderson and 2 more
Re: Turbine 9
I am not aware of any offsite guidance to use virtual mode for other than short duration troubleshooting. Turbine 9 was in virtual mode for approximately 40 hours. This w…
-
30 May 2002
-
29 May 2002
Mark V Walker to Joe Thorpe and 4 more
Re: Preliminary results from analysis of Visupro data for 5/17/02 time period that Gary Verkleeren asked about
I just noticed that I referred to month 5 in some of the dates in memo0529AEP. My apologies. Below is a corrected version that replaces the previous memo0529AEP.
-
29 May 2002
Mark V Walker to Joe Thorpe and 4 more
Preliminary results from analysis of Visupro data for 5/17/02 time period that Gary Verkleeren asked about
Joe, See the file Memo0529AEP. Is there a simple explanation for why the system OK counter continued to increment 44.7 hrs when the turbine blades were pitched out to 80 …
-
29 May 2002
Jeff Duff to Mark Fisher, Mark V Walker, David Miller and 10 more
Re: STARlite Update
Please see the attached STARlite project update. JD
-
29 May 2002
Kurt Anderson to Benjamin Bell and 16 more
Re: FW: GEWE reporting and follow-up
Ben, Rick Winsor's note below has prompted me to provide a timeline with regards to the issue of Zilka's concerns with our Availability calculations. 5/2/02 Rick Winsor s…
-
29 May 2002
Jeff Duff to Mark V Walker, Mark Fisher, Matthew Meyers
Work Request Reminder
Could you fill out any work request forms that have not been completed? I'll have Julie update them into the db so we can keep track. An electronic copy is preferred so w…
-
28 May 2002
-
28 May 2002
-
28 May 2002
Mark V Walker to Kurt Anderson and 6 more
Re: Desert Sky
The contractual availability definition in the owner report is the same used throughout 2002 and implements the contractual availability definition upon which annual avai…
-
28 May 2002
-
28 May 2002
Jeff Duff to Mark V Walker, Mark Fisher
Curtailment software document-FYI
I am not sure if there are new releases to this document. The next email gives an example of the data stored on the plant pc. I'm not sure what will be stored on the park…
-
28 May 2002
Jeff Duff to Mark V Walker, Mark Fisher
Availability reporting
Ignore if this is the second time you got this. Of course, my only involvement with this was through eve's dropping. We should be prepared to discuss what sort of process…
-
24 May 2002
Jeff Duff to David Miller, Patricia Hunter and 8 more
DB Table Additions
To support the data storage of ZMET data here is a proposal for what the table structure should be. In addition, after discussing the status messages it is important to d…
-
23 May 2002
Jeff Duff to Mark V Walker, Mark Fisher
Faults Table
Attached is a summary report showing the following data fields for the faults table. (Fault Number, Include,Fault Description) I've cross referenced this with the spread …
-
22 May 2002
Ronald Brzezinski to rec-scada@enron.com, Mark Fisher and 8 more
Re: Spannungswerte USA
Klaus, I spoke with Hollis. He sounds fine. He is not sure when he will be back to work. They still do not know exactly what happened. I spoke with Mark Fisher. He is in …
-
22 May 2002
Ronald Brzezinski to Klaus Holtel, Mark Fisher and 8 more
Re: Spannungswerte USA
Klaus, I spoke with Hollis. He sounds fine. He is not sure when he will be back to work. They still do not know exactly what happened. I spoke with Mark Fisher. He is in …
-
17 May 2002
Jeff Duff to Mark V Walker, Mark Fisher
List of Validation Categories
These are the levels of validation used to identify wind data in WIMS. Most data is stored at level 2, and cared through 3-4 during an analysis. 1. General range checking…
-
17 May 2002
Hollis Kimbrough to Ilan Caplan and 6 more
Re: April Availability
Ilan, In order to calculate the VA we need the actual VisuPro counter data since we are using an assumed formula for the Vestas Availability. (See attached for this year …
-
15 May 2002
Hollis Kimbrough to Ilan Caplan, Benjamin Bell and 8 more
Vestas Availability 2002
Ilan, Here is our first attempt at a "Vestas Availability" calculation. We did this for the US 1.5 fleet for each month in the year 2002. There are some things you should…
-
15 May 2002
Hollis Kimbrough to Jeff Duff, Mark V Walker, Mark Fisher and 1 more
WHITEWATER - LOCATION & FACILITIES FOR SERVICE CREW
fyi... It is great news to be starting new projects! HK
-
15 May 2002
-
15 May 2002
Mark V Walker to Hollis Kimbrough and 4 more
Re: Calculating "Vestas Availability"
For clarification, the "Vestas availability" you talk about is not specific to Vestas nor is it based on any Vestas contractual availability. This availability is a multi…
-
15 May 2002
Hollis Kimbrough to Mark Fisher, Mark V Walker, Jeff Duff
Calculating "Vestas Availability"
Guys, In an earlier e-mail Ben made the statement: "Have you been able to determine what these numbers would look like using Vestas' definition of availability: Hours of …