29 Nov 2001
Donna Martens to Kelly Allen, Larry Campbell, Earl Chanley and 25 more
Red Rock Regulatory Matrix
Attached is the revised regulatory matrix for Transwestern's Red Rock Expansion project reflecting the request for an extension of time to replace the units at Station 4.…
-
20 Nov 2001
Steve Kalmus to Pallavi Goradia and 12 more
RE: Red Rock (Transwestern) Cashflow
Palu, Two major items affected the cashflow since August: 1.) Air permits have been delayed from August, 2001 to November, 2001. The delay of the air permits impacts cons…
-
20 Nov 2001
Pallavi Goradia to Steve Kalmus and 12 more
RE: Red Rock (Transwestern) Cashflow
Steve, The last forecast you sent the 2001 Red Rock cash flow was $40.7 million, the current forecast is $23.4 million. Please explain the difference of $ 17.3 million. T…
-
20 Nov 2001
Donna Martens to Arnold L. Eisenstein, Larry Campbell, Lorraine Lindberg and 6 more
Station 4
The following request for an extension of time to replace facilities at Station 4 will be filed with FERC on Monday, November 26, 2001. Questions, let me know.
-
16 Nov 2001
Jerry D. Martin to Stanley Horton and 12 more
GTB Payment Status
Enron and IPE received payments totaling $170K since last week's report, and the total paid to date is $3,915K (Enron's portion is $3,476K). GTB is current on all invoice…
-
16 Nov 2001
Donna Martens to Jerry Graves, Gary Maestas and 22 more
RE: Albuquerque Region Outage Report Through December 2002
I see from the attached outage report that the overhauls on the existing units at Station 4 are scheduled to begin April 1, 2002 (instead of March 1, 2002 as previously n…
-
2 Nov 2001
Betty Alexander to Renee Alfaro, Airam Arteaga, beddingfield@enron.com and 86 more
You're Invited!