Red Rock Regulatory Matrix

From
Donna Martens donna.martens@enron.com
To
Kelly Allen, Larry Campbell, Earl Chanley, Arnold L. Eisenstein, Eric Faucheaux, team.flagstaff-sta2@enron.com, team.flagstaff-sta3@enron.com, Gallup-Sta4, Team, cecil.gutierrez@enron.com, Steven Harris, Rich Jolly, William Kendrick
and 16 more team.kingman-sta1@enron.com, Mark Lavine, Lorraine Lindberg, Jerry D. Martin, Mike McCracken, Mary Kay Miller, Maria Pavlou, Keith Petersen, Tony Pryor, Byron Rance, Bill Rapp, David Roensch, John Shafer, Stephen Veatch, Kimberly Watson, Roger Westbrook
Date
Thu, 29 Nov 2001 14:16:39 -0800 (PST)
Attached is the revised regulatory matrix for Transwestern's Red Rock Expansion project reflecting the request for an extension of time to replace the units at Station 4.  Remaining notifications include:

start of construction at Stations 1 & 3, and 4 if applicable (within 10 days), 
end of construction and in-service date (within 10 days),
actual costs (within 6 months after facilities constructed),
noise survey at Stations 3 & 4 (within 60 days after in-service), and
any additional changes in construction and/or mitigation procedures (WOULD REQUIRE A DIRECTOR'S LETTER BEFORE IMPLEMENTING CHANGE).

Questions -please let me know at 7138 in Omaha.  Thanks.  Donna