from:donna.martens@enron.com means Donna Martens (donna.martens@enron.com).
to:roger.westbrook@enron.com means Roger Westbrook (roger.westbrook@enron.com).
-
29 Nov 2001
Donna Martens to Kelly Allen, Larry Campbell, Earl Chanley and 25 more
Red Rock Regulatory Matrix
Attached is the revised regulatory matrix for Transwestern's Red Rock Expansion project reflecting the request for an extension of time to replace the units at Station 4.…
-
1 Nov 2001
Donna Martens to m..allen@enron.com, ken.anderson@enron.com, doug.aschwege@enron.com and 123 more
Omaha - Certificate Status Report
Attached is the Certificate Status Report (Omaha) for November 2001.
-
17 Oct 2001
Donna Martens to Kelly Allen, Larry Campbell, Earl Chanley and 24 more
Red Rock Regulatory Matrix
Attached is the revised regulatory matrix for Transwestern's Red Rock Expansion project reflecting the notice that tree clearing activities commenced on October 11, 2001 …
-
4 Oct 2001
Donna Martens to /o=enron/ou=na/cn=recipients/cn=jfawcet@enron.com, m..allen@enron.com, ken.anderson@enron.com and 124 more
Certificate Status Report
Attached is the Certificate Status Report (Omaha) for October 2001.
-
23 Mar 2001
Donna Martens to Mary Kay Miller, Phil Lowry, Keith Petersen and 27 more
Final Red Rock
Attached is the final document with attachments for the Red Rock filing. Please let me know by 3 P.M. on Friday (3/23) if you have any comments or concerns. Also, please …
-
12 Mar 2001
Donna Martens to Arnold L Eisenstein, Earl Chanley, Larry Campbell and 32 more
Red Rock issues
The following issues need to be addressed for the filing: In regard to the trees within the station yard at Station 2 --- are we correct in saying we will be on "previous…
-
3 Mar 2001
Donna Martens to Rich Jolly, Arnold L Eisenstein, David Roensch and 22 more
Red Rock Expansion
Please review attached redline draft and provide comments and the signed FERC approval form by 2 P.M. on Tuesday, March 6. Questions, let me know. Thanks. Donna
-
24 Feb 2001
Donna Martens to Rich Jolly, Arnold L Eisenstein, David Roensch and 24 more
Red Rock Expansion Filing
Attached is a draft copy of Transwestern's application requesting authorization to abandon the existing units at Stations 1, 2, 3 and 4 and install a 38,000 HP unit at ea…