from:david.delainey@enron.com means David W Delainey (david.delainey@enron.com).
to:mike.miller@enron.com means Mike J Miller (mike.miller@enron.com).
-
3 Jan 2001
David W Delainey to Mike J Miller
Doyle Cost Summary thru 12/28/00
Mike, are we closed out on this job with NEPCO as well. Regards Delainey
-
28 Nov 2000
-
25 Sep 2000
David W Delainey to Mitch Robinson, Kevin M Presto, Mike J Miller and 5 more
Power Systems
Guys, Power Systems has given me a proposal to replace the New Albany and Doyle 7B burners. This could possibly have two benefits: a) elimination of the possibly tainted …
-
25 Sep 2000
David W Delainey to Kevin M Presto, Mike J Miller
Westinghouse LD's for Gleason/Wheatland
Kevin, I am not sure that you will get credit from the buyer for the increased MW's given well known industry issues with the 501F technology. Further, any buyer will pay…
-
13 Sep 2000
David W Delainey to Mike J Miller
(no subject)
Mike, this appears to be a very reasonable settlement - proceed on this basis. I assume this keeps my number in and around the $600 to $615MM for the 2000's all in. Regar…
-
25 Jul 2000
David W Delainey to Mike J Miller and 4 more
Goldendale Turbine
Mike, if you Janet or Dave can cut the deal with Izzo go ahead and speak to him. I don't think there is any practical way to enforce any percieved call we have on Izzo so…
-
11 Jul 2000
David W Delainey to Mike J Miller
Re: Peaker Fee
Thanks Mike - great job on the 2000's and the recovery at Doyle. Lets together once the accounting is completed and determine what is appropriate in fee to pay. Regards D…
-
6 Jul 2000
David W Delainey to Mike J Miller
Peaker Fee
Mike, I want to see the final costs before determining. My understanding is that there is still significant expenses outstanding. Regards Delainey
-
23 Jun 2000
David W Delainey to Robert Virgo and 2 more
Doyle Update 6/23/00
Bob, I know that you made this work !! This recovery plan is exceptional. Regards Delainey
-
15 Jun 2000
David W Delainey to Clay Spears, Mike J Miller, Robert Virgo and 3 more
Doyle Undate
Guys, I am getting the impression that we are having quality control issues - it just sounds sloppy? Am I wrong? Do we need more focused resources? Regards Delainey
-
2 Jun 2000
David W Delainey to Mike J Miller and 4 more
Moore Power Plant status
Mike, why would it cost $450 to $470/kw for the Moore project? It is a 4 unit ABB configuration and the turbine costs appear to be in line with Wilton 7EA's on a kw basis…
-
2 Jun 2000
David W Delainey to Rob Milnthorp, Eric LeDain, Kyle Kitagawa and 8 more
Moore Power Plant status
Rob,this deal is not dead; I am primarly waiting on NEPCO numbers. You should be moving down the road on the deconstruction, refurbishment and movement of the NB machines…
-
17 May 2000
David W Delainey to Mike J Miller
Re: Development Activities
This looks good Mike - I appreciate the efforts. Regard Delainey
-
15 May 2000
David W Delainey to mark.dobler@enron.com, Mitch Robinson, Mike J Miller and 3 more
Peakers
Guys, I appreciate the updates. Please ensure 1) that you, as ENA, are integrated 2) deliver a very clear expectation with EE&CC with a credible plan and 3) that you scre…
-
15 May 2000
David W Delainey to john.normand@enron.com, gavin.gaul@enron.com and 12 more
2000 Peakers
Guys, have we started the mobilization on the tear-down of the two 501FD's at Gleason? Will they be machining the equipment on site - it appears to me that we should not …
-
15 May 2000
David W Delainey to john.normand@enron.com, gavin.gaul@enron.com, Mike J Miller and 8 more
2000 Peakers
Guys, I understand that none of the facilities were available today - I thought we were targeting 750 MW. What is the updated availability schedule for each unit? We are …
-
11 May 2000
David W Delainey to Mike J Miller
Duke
Mike, who is working on the Duke restructuring now? Regards Delainey
-
21 Apr 2000
David W Delainey to Rob Milnthorp, Max Yzaguirre, Janet Dietrich and 24 more
ENA Offsite - May 3rd and 4th, 2000
We are planning an ENA offsite on May 3rd and 4th at Columbia Lakes Resort (West Columbia Texas). You were all contacted to save these dates on your calendars. Both Cliff…