15 May 2000, 17:57 UTC
2000 Peakers
- From
- David W Delainey david.delainey@enron.com
- Bcc
- Larry L Izzo, Mike J Miller, Robert Virgo, mark.dobler@enron.com, Kevin M Presto, Mitch Robinson
- Date
- Mon, 15 May 2000 10:57:00 -0700 (PDT)
Guys, have we started the mobilization on the tear-down of the two 501FD's at Gleason? Will they be machining the equipment on site - it appears to me that we should not let that equipment leave the site if possible. Do we have a credible site rep from Westinghouse for both Wheatland and Gleason? Please advise. Thanks Delainey
Quoted or forwarded from earlier messages
---------------------- Forwarded by David W Delainey/HOU/ECT on 05/15/2000 05:50 PM --------------------------- David W Delainey 05/15/2000 04:42 PM To: John Normand/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, Gavin Gaul/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, Mike J Miller/HOU/ECT@ECT, Robert P Virgo/HOU/ECT@ECT, Mark Dobler/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT cc: Kevin M Presto/HOU/ECT@ECT, Mitch Robinson/Corp/Enron@Enron, Larry L Izzo/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT Subject: 2000 Peakers Guys, I understand that none of the facilities were available today - I thought we were targeting 750 MW. What is the updated availability schedule for each unit? We are only a couple of weeks from June 1. Please advise. Regards Delainey