  1. 18 Apr 2000

    Scot Chambers

    Homestead, FL 6 x 1 LM6000 PC O&M Estimate

    Ben, please find attached an O&M cost estimate for one oil fired 6 x 1 LM6000PC power project located in Homestead, FL. The estimate assumes 1,400 run hours in simple cyc…

  2. 3 Apr 2000

    Scot Chambers

    St Peter, ILL (Ameren) O&M Cost Estimate

    Ben, please find attached the preliminary cost estimate for full O&M services provided at one greenfield, stand alone 2 x LM6000 PC Sprint simple cycle power project loca…

  3. 24 Mar 2000

    Scot Chambers

    UAE - Lowell, MA 5xLM6000 PC Project, Rev 2

    Ben, please find attached revision two to the UAE - Lowell, Massachusetts LM6000 simple cycle peaking facility, which is to be located at an existing, staffed cogen facil…

  4. 22 Mar 2000

    Scot Chambers

    UAE - Lowell, MA 5xLM6000 PC Project

    Ben, please find attached revision one to the UAE - Lowell, Massachusetts LM6000 simple cycle peaking facility, which is to be located at an existing, staffed cogen facil…

  5. 16 Feb 2000

    Scot Chambers

    Rochester Public Utilities Preliminary O&M Estimate

    Ben, please find attached below the preliminary O&M cost estimate for RPU's O&M services to mobilize and operate the 1 x LM6000 peaking facility to be situated in Rochest…

  6. 15 Feb 2000

    Scot Chambers

    Santee Cooper O&M Estimate, Revision 1

    George and Webb, please find attached revision one to the Santee Cooper O&M cost estimate. It is for mobilization and operating period O&M services for one gas fired, 5 x…

  7. 31 Jan 2000

    Scot Chambers

    Lincoln, Nebraska Preliminary O&M Estimate

    Ben, this file here attached is formatted for printing. Please trash the last file in favor of this one. regards, Scot

  8. 31 Jan 2000

    Scot Chambers

    Lincoln, Nebraska Preliminary O&M Estimate

    Ben, please find attached the preliminary O&M estimate for the Lincoln, NE project that we discussed. It shows O&M cost estimates for a 20 year period assuming a stand al…

  9. 24 Jan 2000

    Scot Chambers

    Santee Cooper Project Preliminary O&M Estimate

    George, please find attached the subject preliminary O&M estimate -- consider it with an accuracy of +/- 25% at best. Please review and call should you have questions. re…