24 Mar 2000, 17:36 UTC
UAE - Lowell, MA 5xLM6000 PC Project, Rev 2
- From
- Scot Chambers scot.chambers@enron.com
- Date
- Fri, 24 Mar 2000 09:36:00 -0800 (PST)
Ben, please find attached revision two to the UAE - Lowell, Massachusetts LM6000 simple cycle peaking facility, which is to be located at an existing, staffed cogen facility. The second revisions are due to the following changes in assumptions: 1. Further reduced the staffing costs due to no allocation of labor being assumed from existing plant to peaking plant and the addition of only ONE tech to cover the expansion O&M (per your discussion with UAE). 2. Restated the Annual Routine Maintenance costs components of FOM and VOM to 75% FOM and 25% VOM. Please call if you have questions or want to discuss further. regards, Scot