from:david.delainey@enron.com means David W Delainey (david.delainey@enron.com).
to:mark.dobler@enron.com means mark.dobler@enron.com.
-
9 Feb 2001
David W Delainey to mark.dobler@enron.com
Re: EES Organizational Changes
Mark, thanks for the note - look forward to working with you - you did a great job for me in ENA, I'm sure that will continue. regards Delainey
-
31 Aug 2000
-
8 Aug 2000
David W Delainey to wayne.mays@enron.com, Robert Virgo, mark.dobler@enron.com
Technical Risk Reports
Guys, I would like to schedule a quarterly meeting to review our technical risk as a part of this reporting procedure. Wayne can you set up a meeting for the four of us o…
-
5 Jul 2000
David W Delainey to mark.dobler@enron.com
Re: Genco proposal
Mark, noted - early in the process. regards delainey
-
15 Jun 2000
David W Delainey to Clay Spears, Mike J Miller, Robert Virgo and 3 more
Doyle Undate
Guys, I am getting the impression that we are having quality control issues - it just sounds sloppy? Am I wrong? Do we need more focused resources? Regards Delainey
-
12 Jun 2000
David W Delainey to Raymond Bowen Jr., mark.dobler@enron.com
Nigeria
Guys, the project should be charged market based rates and ENA is not in the business of subsidizing international projects. This is particularily the case if we are not …
-
9 Jun 2000
-
15 May 2000
David W Delainey to mark.dobler@enron.com, Mitch Robinson, Mike J Miller and 3 more
Peakers
Guys, I appreciate the updates. Please ensure 1) that you, as ENA, are integrated 2) deliver a very clear expectation with EE&CC with a credible plan and 3) that you scre…
-
15 May 2000
David W Delainey to john.normand@enron.com, gavin.gaul@enron.com and 12 more
2000 Peakers
Guys, have we started the mobilization on the tear-down of the two 501FD's at Gleason? Will they be machining the equipment on site - it appears to me that we should not …
-
15 May 2000
David W Delainey to john.normand@enron.com, gavin.gaul@enron.com, Mike J Miller and 8 more
2000 Peakers
Guys, I understand that none of the facilities were available today - I thought we were targeting 750 MW. What is the updated availability schedule for each unit? We are …