  1. 15 May 2001

    Peter R. Stark to Max Brown, John Keller, Morgan Gottsponer and 13 more

    RE: Rough Estimate of Costs For Possible TW MAOP Upgrade - 30" Mainline & Loop Lines Sta 5 to Colorado River

    Max, As an alternative to replacing pipe can we consider applying Armour Plate wrap? Peter. Eur Ing Peter R. Stark CEng BSc, BA, MSc, MIM, SenMWeldI, MIMarE. MICorr. Tel:…

  2. 15 May 2001

    Perry Frazier to Mansoor Abdmoulaie, Lorraine Lindberg, Morgan Gottsponer and 4 more

    RE: WT-1 to Sta-9 Capacity

    Thanks for verifying the flow conditions out of WT-1, it appears we might have 35 mmcfd extra capacity above the 550 mmcfd WT-1 discharge capacity, using your assumptions…

  3. 10 May 2001

    Ray Smith to Jerry D. Martin and 34 more

    Red Rock Weekly Report

    1. ACTIVITIES: a. Successful visit to Nuovo Pignone in Italy this week by a team consisting of representatives from E&C, GE and the engineering contractor, UEI. Most of t…

  4. 10 May 2001

    Mansoor Abdmoulaie to Kevin Hyatt and 4 more

    Cost Estimate for MAOP facility requirements

    Kevin I have completed the following costs for the MAOP facility requirements project but have not completed yet the cost of 55,90 and 115 mmcf/d alternatives on the San …

  5. 8 May 2001

    Omaha Helpdesk to adam.dushinske@enron.com, albert.hernandez@enron.com, Alice Johnson and 616 more

    Organization Announcement

    Organization Announcement from Steve Harris: Effective immediately, Kevin Hyatt, Director of the Transwestern Commercial Group, will be joining Eric Gadd of the Asset Dev…

  6. 8 May 2001

    Omaha Helpdesk to allen.cohrs@enron.com, andrea.woody@enron.com, andrew.williams@enron.com and 446 more

    Organization Announcement

    From the desk of Susan Neville I am very pleased to announce that effective May 16, Steve Thomas will transfer to Storage Services as Storage Capacity Manager reporting t…

  7. 7 May 2001

    Lorna Brennan to Courtney Barker, Mike Barry, Joni Bollinger and 87 more

    Questar Holding 3 Open Seasons, North, South and Storage

    Questar Plans WY Storage Project, Pipeline Hub Questar Pipeline launched a major pipeline expansion initiative Tuesday in conjunction with plans announced recently to mov…

  8. 7 May 2001

    Max Brown to John Keller, Morgan Gottsponer, Kevin Hyatt and 13 more

    Rough Estimate of Costs For Possible TW MAOP Upgrade - 30" Mainline & Loop Lines Sta 5 to Colorado River

    As I will be out of town at Gallup NM this week for the excavations planned for TW L-154 line, I will will miss the the meeting on the 10th. I have begun preparation of a…

  9. 1 May 2001

    Jeffery Fawcett to Kirk Ketcherside and 14 more

    Big Sandy Project pressure information

    Kirk, This is really dangerous... having a marketing guy talk to you about engineering matters. However, since we've recently worked with our other power plants to get th…

  10. 27 Apr 2001

    Gary Choquette to Gary Maestas, Kenneth Young and 12 more

    RE: SoCal Tour Update Meeting

    Attached are my planning/optimization notes from the SoCal meeting for the meeting.

  11. 26 Apr 2001

    Jeffery Fawcett to Danny McCarty, Steven Harris, Kevin Hyatt and 12 more

    Enron - Kinder Morgan Hueco Pipeline Project

    Rod Hayslett and I met with Kinder Morgan on 4/25 to discuss the possible commercial structures under which Enron and Kinder could jointly develop, construct and operate …

  12. 26 Apr 2001

    Lorna Brennan to Courtney Barker, Mike Barry, Joni Bollinger and 69 more

    A Revitalized Ruby Pipelines for CIG to California

    CIG Dusts Off Ruby Pipeline, Plans Extension to Sacramento, CA El Paso subsidiary Colorado Interstate Gas is dusting off its Ruby Pipeline project in light of the scrambl…

  13. 24 Apr 2001

    Steven Harris to Mary Kay Miller and 20 more

    Re: TW 10 year capacity posting

    Mary Kay, although we did want to post for 10 years because it helped us in negotiating future contracts, it is no longer necessary to do so for such an extended period. …

  14. 22 Apr 2001

    Arnold Eisenstein to Jerry D. Martin and 32 more

    Red Rock Weekly Report

    1. ACTIVITIES: a. Video conference held with GE/NP to refine turbine SOW b. Marketing held a "bid" last week ending on Friday; results are encourging as multible bids wer…

  15. 19 Apr 2001

    David L. Johnson to Kevin Hyatt, Darrell Schoolcraft, John Keller and 12 more

    TW San Juan Lateral

    Thanks to all for a productive meeting. Here's the synopsis. Please let me know if I've missed anything. 1. Anticipated MAOP changes Bloomfield to Bisti - from 1200 to 12…

  16. 19 Apr 2001

    Max Brown to John Keller, Morgan Gottsponer, Kevin Hyatt and 4 more

    San Juan Upgrade Pressures

    In our original proposal to OPS, the following MAOP's were used: Current MAOP Proposed MAOP Bloomfield to Bisti (approx 37 mi.) 1,200 psi 1,250 psi (75% SMYS) Bisti to Ga…

  17. 19 Apr 2001

    Stanley Horton to Phil Lowry and 12 more

    Re: TW Mainline Capacity & Station 8

    I agree. There have been way too many surprises from this group lately.

  18. 18 Apr 2001

    Lindy Donoho to Jeffery Fawcett and 16 more

    RE: Ameramex - Bloomfield Energy Farm Project - Trigon-Sheehan Information Request

    Will this interconnect actually be with the jointly-owned Blanco Hub facilities (or just in the area of the Blanco Hub)? If we are connecting with the Blanco Hub, we need…

  19. 18 Apr 2001
  20. 17 Apr 2001

    David L. Johnson to David L. Johnson, Steven Harris, Shelley Corman and 10 more

    San Juan Lateral MAOP Upgrade

    We have been asked to expedite a waiver request or whatever regulatory vehicle is appropriate to try to secure an MAOP increase on the TW San Juan Lateral. An initial mee…

  21. 16 Apr 2001

    Stu Asselin" @ENRON to Jeffery Fawcett and 18 more

    RE: Ameramex - Bloomfield Energy Farm Project - Trigon-Sheehan Information Request

    Thanks Jeff - we would definitely like to meet with your team or representatives on site as soon as possible. I'd like to put you in touch with Brett Hurlbut, our Senior …

  22. 9 Apr 2001

    Eric Faucheaux to Kevin Hyatt and 4 more

    Transwestern Pipeline - Gas Quality

    Kevin, if you are okay with this information regarding Market Affiliate Rules, please forward to roger.tietz@enron.com with ENA who has called today and was requesting th…

  23. 6 Apr 2001

    Arnold Eisenstein to d.martin@enron.com and 32 more

    Red Rock Weekly Report

    1. ACTIVITIES: a. FERC Certificate is filed. No questions have been received to date. b Turbine Compressor Letter of Intent was issued to GE/NP for 4 PGT25+ for the Red R…

  24. 6 Apr 2001

    Jean McFarland to david.abraham@enron.com, patricia.andersen@enron.com, Larry J. Anderson and 198 more

    Remote Access via ClickAtHome Systems

    The ClickAtHome portal (www.clickathome.net) will allow employees to access MS Outlook (email, contacts and calendars), eHRonline, PEP, and other employee applications vi…

  25. 5 Apr 2001

    Mansoor Abdmoulaie to Lorraine Lindberg and 30 more

    TW-West Texas Expansion Level "A" release cost estimate 4/5/2001

    This is in response to your request of 3-26-2001 regarding the expansion of TW pipeline system in West Texas. Current Facility Capacity Summary Compression capacity at WT…