to:l..eisenstein@enron.com means Arnold L. Eisenstein (l..eisenstein@enron.com).
-
26 Oct 2001
Ron Matthews to Steven Harris, Kimberly Watson, Lorraine Lindberg and 12 more
Mainline Expansion 250 & 300 MMcf/d Scenarios - Revised
The attached reflect Marketing's request to have interest, overheads, and AFUDC split out for all line items. The revision also includes recent additional input by Engine…
-
25 Oct 2001
Kenneth Young to Eric Faucheaux and 22 more
Re: FW: TW Sta. 4 capacity in 3 unit scenario
Just so that everyone is aware, the units at Station 4 can be operated at levels above their rated horsepower of 4,000 during periods of lower ambient temperatures. Clark…
-
19 Oct 2001
Mark Lavine to Gaby Adamek, James Centilli, Earl Chanley and 16 more
RED ROCK WEEKLY REPORT W/E 10/17/01
Attached is the weekly report for your use and file. Mark Lavine Enron Transportation Services Phn : 713-345-5588 Fax : 713-646-8032 mark.lavine@enron.com
-
18 Oct 2001
Mike McCracken to Donna Martens and 52 more
Re: Red Rock Regulatory Matrix
Off site fabrication tie-in assemblies and scrubber piping for Station 2 has begun at the contractors yard in Bloomfield, NM. We anticipate on site activities related to …
-
17 Oct 2001
Donna Martens to Kelly Allen, Larry Campbell, Earl Chanley and 24 more
Red Rock Regulatory Matrix
Attached is the revised regulatory matrix for Transwestern's Red Rock Expansion project reflecting the notice that tree clearing activities commenced on October 11, 2001 …
-
4 Oct 2001
David Roensch to Ginger Bissey, ronnie.brickman@enron.com, dwain.brown@enron.com and 64 more
Invitation - Albuquerque Regional Meeting
This note is an invitation to the Albuquerque Region Cross Functional meeting to be held November 6th & 7th at the Sheraton Hotel in Albuquerque. In addition, please let …
-
3 Oct 2001
Ron Matthews to John R. Keller, Jerry D. Martin, Doug Cebryk and 6 more
Sun Devil Cost Reconciliation
Attached is a Powerpoint slide showing the differences between the Planning's Level and Engineering's Level A+. Planning's Level A was update to include the current proje…
-
3 Oct 2001
Darrell Schoolcraft to Rich Jolly and 22 more
RE: FW: FW: Gallup Peak Power Avoidance Data Points
I certainly agree. This should be fine. Let me know. DS
-
10 Sep 2001
Kevin Hyatt to Dennis Alters, Nancy Bagot, Larry Campbell and 26 more
Yahoo - Transwestern Pipeline Announces Successful Open Season for Proposed Sun
http://biz.yahoo.com/prnews/010910/dam046_1.html
-
31 Aug 2001
Kevin Hyatt to Dennis Alters, Nancy Bagot, Larry Campbell and 30 more
Sun Devil Open Season Results --CONFIDENTIAL--
Overall, the results from Thursday's open season on our Sun Devil Project were very favorable (see below). Contract terms ranged from two to sixteen years. San Juan 84% s…
-
27 Aug 2001
Todd Ingalls to Rich Jolly, Phil Lowry, Steven Harris and 32 more
Alstom Motor - Gallup Station
The status of the Gallup motor is as follows. I will try to keep everyone updated as I find answers to any questions. Please feel free to call me at 505-238-6099 The moto…
-
22 Aug 2001
Ron Matthews to Kevin Hyatt, Morgan Gottsponer, Doug Cebryk and 4 more
Sun Devil Project - Level B Request "REVISED"
I found a mistake in the first Excel spreadsheet when discussing with Kim Kouri. Cost Estimate Summary sheet (2nd tab) did not add all of the rows down for the San Juan p…
-
21 Aug 2001
Ron Matthews to Kevin Hyatt, Morgan Gottsponer and 2 more
Sun Devil Project - Level B Request
Attached is a Level B request for the Sun Devil project. Keep in mind that this should include only right of way at this time. Details on the compression will probably ch…
-
19 Jul 2001
Eric Faucheaux to James Centilli, Kimberly Watson, Lorraine Lindberg and 16 more
TW Capacity Affected for Red Rock Tie-ins
The following volumes are capacities west of Station 1 that will result from tie-in construction work slated for the Red Rock expansion. Tie-in assemblies will be require…
-
11 Jul 2001
Rich Jolly to Arnie Bailey, Rick Smith, David Roensch and 89 more
San Juan Team Advisor
Effective July 2nd David (Tiny) Roensch) accepted the responsibilities of being the Advisor for the San Juan Team. He will be the Advisor for the Kingman, Flagstaff and S…
-
12 Jun 2001
Kimberly Watson to Jerry D. Martin, Arnold L. Eisenstein, Steven Harris and 4 more
FW: Red Rock: draft letter to GE/NP attached for comment
Jerry and Arnold, Here are our comments on the letter to Nuovo Pignone. Please don't hesitate to call me if you need additional information or have any questions. Thank y…
-
7 Jun 2001
Phil Lowry to Stanley Horton, Danny McCarty, Steven Harris and 22 more
Project Red Rock Update and Alternatives
Per discussions with Steve Harris we have re-estimated volumes and costs for a smaller version of Project Red Rock. We have studied two scenarios and the results are as f…