to:ben.asante@enron.com means Ben Asante (ben.asante@enron.com).
-
14 Feb 2002
Jerry Graves to Jesse Alvarado, Roy Armitage, team.artesia@enron.com and 73 more
Albuquerque Region Outage Report Through December 2002
Please review the attached outage report. Jerry Graves 713-345-8923
-
13 Feb 2002
Ron Matthews to Bill Rapp and 12 more
Bloomfield Inlet Air Cooler Project
Bill, The following is a brief desciption of the above mentioned project. The Bloomfield air inlet cooler project consist of the installation of evaporative pads around t…
-
13 Feb 2002
Jerry Graves to ken.anderson@enron.com, Ben Asante, scott.bade@enron.com and 80 more
Beatrice, and Minneapolis Region Outage Reports Through December 2002
Please review the attached outage report that pertains to your region. If you have any questions, please give me a call. Jerry Graves 713-345-8923 (Office) 713-646-2584 (…
-
13 Feb 2002
Jerry Graves to Jesse Alvarado, Roy Armitage, Ben Asante and 85 more
Amarillo, and Midland, Region OutageRreports Through December 2002
Please review the attached outage report that pertains to your region. If you have any questions, please give me a call. Jerry Graves 713-345-8923 (Office) 713-646-2584 (…
-
12 Feb 2002
Mansoor Abdmoulaie to Kenneth Young and 24 more
Bloomfield Units 1 & 2 Air Coolers -----Level " C" Construction Release
Ken, Please proceed to issue a Work Order to install inlet air cooling facilities on Units 1 & 2 at the Bloomfield Compressor Station. The ambient temperature for this ar…
-
12 Feb 2002
Jerry Graves to Gary Choquette, David Roensch, Team San-Juan-LaPlata and 5 more
RE: La Plata Unit Fuel Valve Change-out
I don't have an outage for fuel valve replacement yet. Would that need to be done during the scheduled turn around? Jerry
-
12 Feb 2002
Audrey Robertson to Dennis Alters, Ben Asante, Ramona Betancourt and 26 more
Steve's Staff Meeting - Holiday Change
Due to the President's Day Holiday on next Monday, February 18, Steve will hold his staff meeting on Tuesday, February 19, same time, same location. As a courtesy to all …
-
12 Feb 2002
Ron Matthews to Michelle Lokay, James Centilli and 4 more
Bakersfield Power Plants Project
Attached is an Excel spreadsheet showing the costs to build a 20-mile 20" pipeline from PG&E to Bakersfield. Thereis a sheet for the pipeline and one for the measurement.…
-
12 Feb 2002
Todd Ingalls to Gary Choquette, David Roensch, Team San-Juan-LaPlata and 6 more
RE: La Plata Unit Fuel Valve Change-out
Nowhere Yet. I still have it on my plans to do. Todd
-
12 Feb 2002
Ron Matthews to acook@utilicorp.com and 6 more
Transwestern Historical Pressures - Kingman
Alan, Attached is an Excel spreadsheet with historical pressures at two points. The column titled south of Kingman will be the closes point off TW's mainline to the Red L…
-
12 Feb 2002
Gary Choquette to David Roensch, Team San-Juan-LaPlata, Todd Ingalls and 6 more
La Plata Unit Fuel Valve Change-out
Has there been an outage scheduled to replace the fuel valve on unit 2 at La Plata? Todd, where do we stand with the station control modifications?
-
11 Feb 2002
David Roensch to Ben Asante, Darrell Schoolcraft, Ron Matthews and 4 more
RE: San Juan Pig
A conf. call has been set up for Tuesday February 12th at 9:00 A.M. Central time. 877-795-3687 pin 346994 10 ports will be available
-
9 Feb 2002
David Roensch to Ben Asante, Jeff Whippo, John Sturn and 3 more
RE: San Juan Pig
I would like to schedule a conf. call to discuss this next week (Tuesday?) if you all would be available. Let me know and I will make the arrangements. Thanks
-
8 Feb 2002
Ron Matthews to Lindy Donoho and 6 more
TW History
This is very lengthy but the best I can do in a rush. Didn't have time to research all of the times and miles of pipe but did the best I could. If we need the details, le…
-
8 Feb 2002
Ben Asante to David Roensch and 12 more
RE: San Juan Pig
David, Here is our efficiency analysis from the online model. This is just for the Bisti to Gallup section. The other sections have comparable results. You can see that b…
-
8 Feb 2002
Sharon Brown to Ben Asante, Arnie Bailey, scott.billingsley@enron.com and 45 more
Feb. 7 Log
Sharon Brown ETS Gas Control 713-853-5660
-
8 Feb 2002
David Roensch to Ben Asante and 4 more
RE: San Juan Pig
Ben, I understand the team collected pressure data at the mainline valves on the SJ lateral and forwarded to you all Tuesday. Have you had the opportunity to calculate th…
-
7 Feb 2002
Jerry Graves to team.ashland@enron.com, team.beaver-mach-shop@enron.com, team.beaver-plant@enron.com and 122 more
Bushton Universe, DesMoines, and Dakota Region Outage Reports Through December 2002
Please review the attached outage report that pertains to your region. If you have any questions, please give me a call. Jerry Graves 713-345-8923 (Office) 713-646-2584 (…
-
7 Feb 2002
Jerry Graves to Jesse Alvarado, Roy Armitage, team.artesia@enron.com and 73 more
Albuquerque Region Outage Report through December 2002
Please review the attached outage report. Jerry Graves 713-345-8923
-
7 Feb 2002
Zelda Paschal to Steven Harris, Kimberly Watson, John R. Keller and 31 more
2002 Initiatives Meeting
Due to a conflict of recently scheduled meetings, Friday's 2002 Initiatives Meeting will be cancelled. A notice will be sent out later regarding the status of remaining I…
-
7 Feb 2002
Sharon Brown to Ben Asante, Arnie Bailey, scott.billingsley@enron.com and 45 more
Feb. 6 Log
Sharon Brown ETS Gas Control 713-853-5660
-
6 Feb 2002
Jerry Graves to Jesse Alvarado, Roy Armitage, Ben Asante and 136 more
Amarillo, Beatrice, Midland, and Minneapolis Region Outage Reports Through December 2002
Please review the attached outage report that pertains to your region. If you have any questions, please give me a call. Jerry Graves 713-345-8923
-
6 Feb 2002
Sharon Brown to Ben Asante, Arnie Bailey, scott.billingsley@enron.com and 45 more
Feb. 5 Log
Sharon Brown ETS Gas Control 713-853-5660
-
6 Feb 2002
Sharon Brown to Ben Asante, Arnie Bailey, scott.billingsley@enron.com and 45 more
Feb. 4 Log
Sharon Brown ETS Gas Control 713-853-5660
-
4 Feb 2002
Jeanne Licciardo to Lisa Sawyer, don.stacy@enron.com, Kimberly Watson and 8 more
RE: February -1 Capacity Analysis System ( CAS) meeting
Attached are the minutes from the meeting and also the Production log. Please review and let me know if I have stated anything incorrectly. I will be out of the office st…