to:mike.coleman@enron.com means Mike Coleman (mike.coleman@enron.com).
-
3 Apr 2001
Lillian Carroll to Louise Kitchen, Max Yzaguirre, Robert Virgo and 15 more
PROJECT VITRO REVIEW MEETING
Please mark your calendars for the following meeting: Date: April 20, 2001 Location: EB3321 Time: 10:00 AM Subject: Vitro Project Attendees: Brian Redmond Louise Kitchen …
-
3 Apr 2001
Larry Bishop to Ben Jacoby, Kay Mann, Mike Coleman and 9 more
Ft. Pierce EPC Term Sheet
Attached is a VERY PRELIMINARY draft of the EPC Term Sheet for review and comment. It has a lot of hole's, and needs to be read in that light. I will give it more time an…
-
2 Apr 2001
Lillian Carroll to Ozzie Pagan, David Fairley, Ben Jacoby and 15 more
Ft. Pierce Project Review Meeting
Please note new time and location for the Ft. Pierce Project Review Meeting: Date: April 17th Time: 1:00 PM Location: EB3321 Attendees: Brian Redmond Louise Kitchen John …
-
29 Mar 2001
Lillian Carroll to Louise Kitchen, Max Yzaguirre, Robert Virgo and 8 more
Project Vitro Review Meeting
Please let me know if you are available for a meeting on April 19th at 10:00 AM regarding the Vitro Project. A conference call will be set up for Max Yzaguirre from Mexic…
-
24 Mar 2001
Kevin Jolly to John J Lavorato, Mark Frevert, W David Duran and 26 more
3/23/01 Turbine Position Report
Please call Chip Schneider at 3-1789 or Kevin Jolly at 5-7147 if you have any questions.
-
24 Mar 2001
Brian Redmond to Ozzie Pagan, David Fairley, Ben Jacoby and 7 more
Ft. Pierce
Ozzie: As a follow up to our phone conversation, how about scheduling the Ft. Pierce project review meeting during the second week in April? The objective of the meeting …
-
22 Mar 2001
Max Yzaguirre to Brian Redmond and 12 more
Re:
Brian: Sounds like a good idea, and I'll be happy to attend. If it's OK with you, I'd like to schedule this for some time after the end of March. Steve Irvin and Marc Sab…
-
21 Mar 2001
Brian Redmond to Max Yzaguirre and 10 more
(no subject)
Max: I would like to organize a Vitro project review meeting during the next several weeks focusing on the technical risk in the deal and the mitigation measures we takin…
-
15 Mar 2001
Ben Jacoby to Kay Mann, Lisa Bills, Roseann Engeldorf and 6 more
Turbine 1 and 2 Purchase Agreement
As you may know, we are proceeding with development of the Ft. Pierce, FL project using one of the MHI 501F turbines. Several contract issues need to be sorted out with M…
-
12 Mar 2001
Ron Coker to Greg Whalley, Louise Kitchen, Brian Redmond and 35 more
Pastoria Update - Revised Power Asset Development DASH
The Pastoria DASH each of you signed last week has been modified at the request of Jeff Skilling and Rebecca Carter. Late Friday afternoon, West Power was advised to valu…
-
12 Mar 2001
Ron Coker to Greg Whalley, Louise Kitchen, Brian Redmond and 35 more
Pastoria Update - Revised Power Asset Development DASH
The Pastoria DASH each of you signed last week has been modified at the request of Jeff Skilling and Rebecca Carter. Late Friday afternoon, West Power was advised to valu…
-
14 Feb 2001
David W Delainey to Mike Coleman
Re: Access to MHI
Mike, please let Brian know if there is a problem and let him rectify. It is difficult for me to be responsive otherwise. Thanks Dave
-
24 Jan 2001
Kay Mann to Catherine Clark, Sheila Tweed, Roseann Engeldorf and 5 more
My suggested changes to bullet points re: legal role
ENA Legal (TBD) 1. ENA Legal is responsible for deal documentation and legal sign off for the transaction, and is typically responsible for all transaction-related agreem…
-
14 Dec 2000
Stuart Zisman to chris.kirksey@austinenergy.com and 10 more
Assignment of Equipment
Chris, Attached is a draft of a conveyance document which is intended to transfer ownership of the turbines and other equipment to the City of Austin and Enron Sandhill L…
-
13 Dec 2000
Eric Boyt to Stuart Zisman and 16 more
Re: Austin Energy Amendments
I agree with Stuart regarding the preference for the Assignment, Bill of Sale and Conveyance. It is a little confusing as to why AE, who was a party to the original Parti…
-
12 Dec 2000
Stuart Zisman to Eric Boyt, Billy Lemmons Jr., james.ducote@enron.com and 4 more
Austin Energy Amendments
In response to the attached email, I told Hal that I would prefer the Assignment, Bill of Sale and Conveyance. To me, that is easier and cleaner (a tax auditor would like…
-
30 Nov 2000
Stuart Zisman to Kay Mann and 4 more
Re: Authorization for Haul & Install Option at Austin Project
Kay, This appears to be relatively simple ( and I know that we wanted to have ABB haul and install) but I am not at all familiar with the ABB Contract. Would you mind tak…
-
29 Nov 2000
Scott Laidlaw to carl.stendebach@abbpge.com, denis.peranic@chkra.mail.abb.com, coaustin@wt.net and 72 more
Warm Fuzzies from B.W.
these are neat. regards. scott. FIVE GREAT LESSONS: 1 - Most Important Lesson - During my second month of nursing school, our professor gave us a pop quiz. I was a consci…
-
27 Nov 2000
Eric Boyt to Mike Coleman, Ben Jacoby, Jeffrey Keenan and 8 more
City of Austin Agreement - Update
Ben/Mike/Jeff, Here is a quick update and a request for your assistance: On Wednesday, November 22, ENA sent West LB a 5-day notice indicating our intent to exercise the …
-
13 Nov 2000
Kathleen Clark to Mike Coleman and 6 more
Authorization for Haul & Install Option at Austin Project
Mike: Attached is a draft letter which provides authorization to ABB for the haul & install option at Austin. After it has been signed, please send me a copy for my files…
-
10 Nov 2000
David W Delainey to Mike Coleman
Enron North America to Enron Americas--Redefinition of Technical Role?
Mike, duly noted; however, there will be at this point no change in the scope and function of Redmond's group. Thanks Delainey
-
13 Oct 2000
Scott Laidlaw to John Schwartzenburg, david.bargainer@enron.com, Brian D Barto and 5 more
siemens westinghouse damaged generator
everyone - greetings. the attached letters are drafts for your review and comment. we'll clean up the transmittal with letterhead at time of sending. our intent is to sen…
-
6 Sep 2000
Mathew Gimble to David Fairley, Ozzie Pagan, Rusty Stevens and 32 more
Updated Timetable
Attached is an updated Timetable detailing the critical path issues of the Fort Pierce Repowering Project. Specifically, note items scheduled for completion during the ne…
-
22 Aug 2000
Kay Mann to Mike Coleman, Jeffrey Keenan, john.moore@enron.com
501D for Edgecombe Energy Project
Hi Guys, Is the 501D in storage? If not, when will it be delivered? I'm asking in connection with information to be provided in the CPCN process. Thanks, Kay
-
21 Aug 2000
Mathew Gimble to David Fairley, Janet Dietrich, Ozzie Pagan and 28 more
Fort Pierce Press Release
Attached is a copy of the Fort Pierce Press Release included in the 8/18 edition of the Fort Pierce Tribune. I have also included an updated version of the Deal Team list…