22 Feb 2002
newsletter@rigzone.com" @ENRON to Darrell Schoolcraft
RIGZONE Industry News
[IMAGE] Monday February 25, 2002 [IMAGE] [IMAGE] [IMAGE] [IMAGE] RIGZONE [IMAGE] [IMAGE] [IMAGE] [IMAGE] [IMAGE] home | news | search | maps | data | jobs | market | stor…
-
22 Feb 2002
Jerry Graves to Lynn Blair, scott.clark@enron.com, Shelley Corman and 33 more
NNG Outage Weekly
The Outages attached below have some potential flow impact, or are points of interest. (NNG Only) If you need to be removed from this email listing please let me know. Je…
-
22 Feb 2002
Jerry Graves to Team Bushton-Maintenance, Darrell Schoolcraft, Gary Spraggins and 5 more
RE: Bushton Unit 31 Outage
Thanks Randy, we appreciate it. Jerry
-
22 Feb 2002
John Sturn to Ben Asante, Gary Choquette, Jerry Graves and 11 more
Bloomfield DRA Re-Application
I have been asked to proceed with plans for the installation of DRA on the SJ lateral for around mid-April. I am trying to schedule a conference call next week to discuss…
-
22 Feb 2002
Jodie Floyd to Frankie Adams, Dennis Alters, Gary E. Anderson and 120 more
NNG Measurement Log for Feb. 2002
Attached in the NNG Measurement Log for Feb. 2002. I have only attached the Log items for Feb. 02 to see this will try and eliminate the trouble some field locations are …
-
22 Feb 2002
Dale Ratliff to controllers.dl-ets@enron.com
Permian linepack
It is no longer necessary to inhibit the suction and discharge pressures at Seminole and Brownfield for correct Permian linepack. These point have been enabled in the GUI…
-
22 Feb 2002
Team Bushton-Maintenance to Jerry Graves, Darrell Schoolcraft, Gary Spraggins and 4 more
RE: Bushton Unit 31 Outage
Jerry, Attached is a revision to push the outage back one week. In fact it would fit my schedule better this way. Thanks Randy Peschka From: Jerry Graves/ENRON@enronXgate…
-
22 Feb 2002
Linda Trevino to TK Lohman, Lindy Donoho, Lorraine Lindberg and 23 more
New TW Contract/Capacity Release System Demo
The new TW Contract/Capacity Release system is due to be implemented the weekend of March 9, 2002. We will be offering training/demo's of the new system for internal user…
-
22 Feb 2002
Hasan Kedwaii to Jeanne Licciardo, Ramona Betancourt, Linda Trevino and 10 more
Task Status Report: Bloomfield Issues - Please review meeting minutes at the bottom
-----Original Task----- Subject: Bloomfield Issues Due date: Fri 2/22/2002 Status: Not Started Attendees: Licciardo, Jeanne; Betancourt, Ramona ; Trevino, Linda; Kedwaii,…
-
22 Feb 2002
Perry Frazier to Lorraine Lindberg, Dennis Lee, Darrell Schoolcraft
RE: Duke k#27579
Lorraine: I don't see a problem with this move during the outage. Let's get Darrells opinion on the matter. PT 3-0667
-
22 Feb 2002
MaryAnne Schneider" @ENRON to Amy Mulligan, Bert Hernandez, Beverly Miller and 14 more
Griffith Noms for the Weekend
Attached is our nomination form for the Griffith Power Plant for gas days Saturday, Feb. 23, 2002 through Monday, Feb. 25, 2002. It changes each day. Please let me know i…
-
22 Feb 2002
Lorraine Lindberg to Perry Frazier, Dennis Lee, Darrell Schoolcraft
Duke k#27579
During the Crawford outage scheduled for 3/5-7, Duke has requested to move its primary receipt point from Crawford to the Duke WT-1 receipt point. Since there will be no …
-
22 Feb 2002
Randy Janzen to Lynn Blair, controllers.dl-ets@enron.com, Cara Vaughan and 10 more
POI 152 - OneOk Westex Reeves
I have been working closely with OneOk Westex this month in order to balance their OBA at Reeves and to date we are still approximately 17,000 dth over delivered to them.…
-
22 Feb 2002
Randy Janzen to controllers.dl-ets@enron.com, Cara Vaughan, Chris Greaney and 9 more
FW: Lamar Nominations (Feb 23-25)
-----Original Message----- From: Jamie_K_Schnorf@fpl.com@ENRON On Behalf Of Jamie_K_Schnorf@fpl.com Sent: Friday, February 22, 2002 9:48 AM To: Art_R_Morris@fpl.com; Spra…
-
22 Feb 2002
Team San-Juan to Rich Jolly, David Roensch, Darrell Schoolcraft and 2 more
Pig Run for San Juan Lat
I called Darrell (2-22-02)to set up a day to run pig down the San Juan Lat. He said we will look at it next week. When we get a day we will forward it to all of you. Than…
-
22 Feb 2002
Enron General Announcements to dl-ga-all_domestic@enron.com
Outlook Web Access Outage
Enron's external Outlook Web Access (OWA) (http://mail.enron.com) will be unavailable starting at 11:00 a.m. today until about 12:00 p.m. for emergency network maintenanc…
-
22 Feb 2002
Gary Spraggins to controllers.dl-ets@enron.com, team.ogden-field@enron.com, John Sturn
Ogden Operations conf.call
The Ogden Operations conf. call has been scheduled for 10:30 A.M. today. The number is 1-877-795-3687 code 527126. Thanks Gary
-
22 Feb 2002
Terry Kowalke to patrick.barry@enron.com, Jean Blair, Randy Bryan and 28 more
FW: Demarc Numbers
To all reps, please start pulling the Demarc Numbers and passing it on to the appropriate person. This will be required until Gas Control says otherwise. If you have ques…
-
22 Feb 2002
Darrell Schoolcraft to dl-etsgascontrollers@enron.com
FW: Tw imbal summary
-----Original Message----- From: Hanagriff, Richard Sent: Thursday, February 21, 2002 9:12 PM To: Schoolcraft, Darrell; Lindberg, Lorraine Subject: Tw imbal summary Lorra…
-
22 Feb 2002
Gary Spraggins to Jerry Graves, Team Bushton-Maintenance, team.bushton-operations@enron.com and 4 more
RE: Bushton Unit 31 Outage
Currently the Northend temperatures show to drop from mid 30's Saturday to 19 degrees Sunday and 10 degrees for system weighted temperature for Monday and start back up i…
-
22 Feb 2002
Sharon Brown to Dale Ratliff, Darrell Schoolcraft, Gary Spraggins
FW: Dr. Office Re-opens
Sorry, forgot you on the distribution
-
22 Feb 2002
Richard Hanagriff to Darrell Schoolcraft, Lorraine Lindberg
Tw imbal summary
Lorraine Note that NGPL is making payback this month
-
21 Feb 2002
newsletter@rigzone.com" @ENRON to Darrell Schoolcraft
RIGZONE Industry News
[IMAGE] Friday February 22, 2002 [IMAGE] [IMAGE] [IMAGE] [IMAGE] RIGZONE [IMAGE] [IMAGE] [IMAGE] [IMAGE] [IMAGE] home | news | search | maps | data | jobs | market | stor…
-
21 Feb 2002
Jerry Graves to Team Bushton-Maintenance, team.bushton-operations@enron.com, Darrell Schoolcraft and 4 more
RE: Bushton Unit 31 Outage
Randy, the time table you have for this outage is 02/26 to 02/28 to replace a section of the exhaust header. If we have cold temps the first part of the week, can this ou…
-
21 Feb 2002
Jerry Graves to Jesse Alvarado, Roy Armitage, team.artesia@enron.com and 72 more
Albuquerque Region Outage Report Through December 2002
Please review the attached outage report. Jerry Graves 713-345-8923