Jerry, Attached is a revision to push the outage back one week. In fact it would fit my schedule better this way. Thanks Randy Peschka From: Jerry Graves/ENRON@enronXgate on 02/21/2002 04:23 PM To: Team Bushton-Maintenance/ET&S/Enron@ENRON, Team Bushton-Operations/ET&S/Enron@ENRON, Darrell Schoolcraft/ENRON@enronXgate, Gary Spraggins/ENRON@enronXgate, Steven January/ENRON@enronXgate cc: Mike Peschka/ET&S/Enron@ENRON Subject: RE: Bushton Unit 31 Outage Randy, the time table you have for this outage is 02/26 to 02/28 to replace a section of the exhaust header. If we have cold temps the first part of the week, can this outage be pushed back a few days? Jerry
Quoted or forwarded from earlier messages
-----Original Message----- From: Bushton-Maintenance, Team Sent: Thursday, February 21, 2002 3:22 PM To: Bushton-Operations, Team; Graves, Jerry; Schoolcraft, Darrell; Spraggins, Gary Cc: Bushton-Maintenance, Team; Peschka, Mike Subject: Bushton Unit 31 Outage Attachment Thanks Randy Peschka << File: 31exhaustheader.doc >>