RE: Flagstaff Trip Rescheduled for July 24 - 26th
John, I was just thinking that if this deconning becomes a routene activity for us and PG&E, we might want to consider breaking in a company that is less expensive, can m…
-
3 Jul 2001
Kevin Hyatt to steve@enron.com, Lindy Donoho, Jeffery Fawcett and 6 more
Oneok Westex Transmission Interconnect, Ward County, TX
We have finalized negotiations with Oneok Westex on the new 200,000 MMBtu/d interconnect with TW in Ward County, TX. The final agreement has been emailed to them for thei…
-
22 Jun 2001
Team Kingman-Needles to Rich Jolly, team.kingman-sta1@enron.com, team.kingman@enron.com and 13 more
PGE sample results
See attached for this months sample run.
-
21 Jun 2001
Darrell Schoolcraft to Gallup-Sta4, Team, Jerry Graves, Rich Jolly and 1 more
RE: station4 outage req.
1. On your first request for down time next week. You may have an opportunity this weekend 23, or 24 depending on the volumes. We can communicate this to your Team Friday…
-
21 Jun 2001
Louis Soldano to David Nutt, Larry Campbell, John Shafer and 6 more
NMED Compliance Order
Privileged & Confidential Attorney - Client Communication I just spoke with Mr. Charles de Saillan, Asst. General Counsel for the NMED, concerning the referenced Complian…
-
19 Jun 2001
Max Brown to laura.kunkel@enron.com and 10 more
FW: Transwestern 50479-30A and 30B
Laura, Can you shed any light on this?
-
19 Jun 2001
Larry Campbell to John Shafer, William Kendrick and 10 more
Compliance Order, P-1 C/S
Transwestern received a Compliance Order from the State of New Mexico, Air Quality Bureau, for an outstanding turbine replacement activity at the P-1 C/S which occurred i…
-
15 Jun 2001
-
13 Jun 2001
Darrell Schoolcraft to Gary Spraggins and 6 more
Re: Pigging from P-2 to P-3
I spoke to the guys in the field last week when our deliveries went up and we made the decision to run the pigs. It was passed on to us that the fluids in the line were h…
-
12 Jun 2001
Team Kingman-Needles to Rich Jolly, team.kingman-sta1@enron.com, team.kingman@enron.com and 13 more
PGE sample run
We had to change labs so i don't know when the results will be back. Here are the liquids gathered for this months sample run. See attached. Thanks, Randy
-
6 Jun 2001
Michael Adewumi to Larry Campbell and 14 more
RE: status, PCB pipeline modeling study
Dear Larry: We are currently completing the improved modeling to include the effect of flow regimes, which I am sure that you recall that in our meeting the last time, we…
-
31 May 2001
Darrell Schoolcraft to Kenneth Young and 38 more
Re: TW 1090 Project Schedule - Stations 1-4
We need know everyday units need to be taken down and for how long. Depending on system conditions we may have to allocate. DS From: Kenneth Young 05/31/2001 09:36 AM To:…
-
31 May 2001
Darrell Schoolcraft to Kenneth Young and 38 more
Re: TW 1090 Project Schedule - Stations 1-4
Ken, We currently have a unit down at Station 4. If you need to work on something now is the time to do it and not wait until June. DS From: Kenneth Young 05/30/2001 11:5…
-
31 May 2001
Darrell Schoolcraft to Kenneth Young and 38 more
Re: TW 1090 Project - Stations 1-4
What is the time frame these units need to be down. There are no postings for volume deductions. Please someone give me some ideas. Thanks Ds From: Kenneth Young 05/30/20…
-
24 May 2001
Darrell Schoolcraft to james.moore@enron.com and 26 more
Re: Concern - Possible Change In Smartpigging Dates
Right now it looks like we can run station 9, station 7, station 6 or station 5. We will just have to see what we have scheduled for the day. This will allow us to set ou…
-
24 May 2001
Darrell Schoolcraft to Arnie Bailey and 22 more
Re: Concern - Possible Change In Smartpigging Dates
You are correct looking at the models Ken Chow ran before he left was between 175 to 225 this will allow the pig to move approx. between 5 to 6 miles an hour. DS From: Ar…
-
24 May 2001
Larry Campbell to Michael Adewumi and 14 more
RE: status, PCB pipeline modeling study
Michael, I will be discussing with John and others in the near future about the status of the study. When will your progress report be ready for review? It might be a goo…
-
24 May 2001
Darrell Schoolcraft to Max Brown and 22 more
Re: Concern - Possible Change In Smartpigging Dates
Is there a reason we think we will need to run station 8. I think with the volumes we will have to move to insure 6 miles and hour for the smart pig will be approx. 100 t…
-
24 May 2001
Larry Campbell to Byron Rance and 10 more
Re: Building Colors
Byron/Tiny, I spoke to Ken Jacobs with the Forest Service and have attached his e mail below concerning the Forest Sevice's choice for the building. I have informed him t…
-
24 May 2001
Michael Adewumi to Larry Campbell and 14 more
RE: status, PCB pipeline modeling study
Hi Larry: Sorry for the delayed response. I have just got back from an overseas trip yesterday. I am in the process of preparing a progress report for you. We have obtain…
-
21 May 2001
Larry Campbell to team.flagstaff-sta2@enron.com, Team Flagstaff and 8 more
Tree Removal, Sta. 2
I spoke with Ken Jacobs, with the Forest Service in Flagstaff, concerning his agencies approval for the turbine construction at Station 2. As a condition of the approval …
-
21 May 2001
Team Kingman-Needles to Rich Jolly, team.kingman-sta1@enron.com, team.kingman@enron.com and 13 more
PG&E Samples
See attached PG&E sample results.
-
18 May 2001
Larry Campbell to Lorraine Lindberg, Team Laguna, Team Mountainair and 4 more
RE: PCB sampling at Rio Puerco
Laguna and or Moutainair team, because I dont know which team is responsible for the Belen delivery point, would someone check on liquids at this location and if present,…
-
17 May 2001
Kim Ladish to Rich Jolly, David Roensch, Larry Campbell and 3 more
FW: June 18 - 20 Flagstaff Trip
Hi guys! The itinerary for Randy and John is attached for your June 18 - 20 trip. Thank you, Kim Ladish 713-345-5863 SERVICE DATE FROM TO DEPART ARRIVE AMERICA WEST AIRLI…
-
15 May 2001
Peter R. Stark to Max Brown, John Keller, Morgan Gottsponer and 13 more
RE: Rough Estimate of Costs For Possible TW MAOP Upgrade - 30" Mainline & Loop Lines Sta 5 to Colorado River
Max, As an alternative to replacing pipe can we consider applying Armour Plate wrap? Peter. Eur Ing Peter R. Stark CEng BSc, BA, MSc, MIM, SenMWeldI, MIMarE. MICorr. Tel:…