Oneok Westex Transmission Interconnect, Ward County, TX
- From
- Kevin Hyatt kevin.hyatt@enron.com
- To
- steve@enron.com, Lindy Donoho, Jeffery Fawcett, Lorraine Lindberg, TK Lohman, Michelle Lokay, Audrey Robertson
- Cc
- Rich Jolly
- Bcc
- Rich Jolly
- Date
- Tue, 3 Jul 2001 08:56:33 -0700 (PDT)
We have finalized negotiations with Oneok Westex on the new 200,000 MMBtu/d interconnect with TW in Ward County, TX. The final agreement has been emailed to them for their signature. TW's costs are approximately $28,000 including the gross up for tax purposes which is fully reimbursable from Oneok. The meter is a high-capacity ultrasonic meter which will take gas from the Oneok Red River system and deliver it into TW south of WT-2. The POI is #78161. Oneok says they are ready to flow; I have not heard yet from our field whether or not TW is ready. Let me know if you have questions. Kevin Hyatt