7 Nov 2001, 18:29 UTC
RE: Big Sandy Delivery Point Construction and Operating Agreement - Revised
- From
- Ketcherside, Kirk L (IGI Resources) ketchekl@bp.com
- Date
- Wed, 7 Nov 2001 10:29:31 -0800 (PST)
Hi Kim. Just wanted to let you know that the Big Sandy project is awaiting a vote yes/no from the ACC Commissioners on the 26th of this month. At this point, I think it is likely that the project will not be approved, and may opt to resubmit. Counsel for Caithness in the appeal process suggested a negative bias in the ACC Power Plant Siting Committee, and that was not well received by the Commissioners....major blunder. I will keep you updated as this continues to develop. If a yes vote, then we will proceed immediately with interconnect agreement, etc. Best regards, Kirk