16 May 2001, 15:22 UTC
(no subject)
- From
- Derek Davies davies@enron.com
- Date
- Wed, 16 May 2001 08:22:39 -0700 (PDT)
John, I've been approached by a couple of loads in Montana totalling 50-75 MWs. Zufferli and I did some rough math on the costs of transmission and what our implied offer would be and haven't heard back from the counterparties. I think that you need more critical mass to make a project work. Derek
Quoted or forwarded from earlier messages
---------------------- Forwarded by Derek Davies/CAL/ECT on 05/16/2001 09:16 AM --------------------------- From: John J Lavorato/ENRON@enronXgate on 05/13/2001 10:04 PM CDT To: Derek Davies/CAL/ECT@ECT cc: Subject: Derek Fed Ex the PPA sales pitch to me. Also, I read in the newspaper that Montana was tight for power. I couldn't tell wether they are tight or the price is just high. Can we sell long term power to a counterparty or two or three in Montana and build a line? John