Enron email

Algorithmic Indexing

12 Oct 2001, 11:49 UTC

Expidited Request to EPA for Review

From
Larry Campbell larry.campbell@enron.com
To
Shudeish Mahadev, bhargava.prabhat@ev.state.az.us
Cc
William Kendrick, Van Wolf, Jerry D Martin, Richard Melton
Bcc
William Kendrick, Van Wolf, Jerry D Martin, Richard Melton
Date
Fri, 12 Oct 2001 04:49:00 -0700 (PDT)
Shudeish, I spoke with Roger Kohn, Region IX EPA permit engineer, about the 
time his agency will take to do the air permit reveiw for Kingman and 
Flagstaff.  He stated that EPA normally gets the allowed 45 days to do the 
permit review, however, at the request of the state agency, his office will 
do an expidited review.  Because of the urgency of Transwetern desiring to 
initiate construction, by this email, I am asking the ADEQ to request  an 
expidited review  of the Kingman and Flagstaff air permits from the EPA.

Again, thanks for your work and effort that you have put in on this project.