14 Sep 2000, 11:15 UTC
CPUC
- From
- Thane Twiggs thane.twiggs@enron.com
- Date
- Thu, 14 Sep 2000 04:15:00 -0700 (PDT)
A couple of folks have told me that SDG&E wants to go to the commission to get a "pre-prudency" type approval with the CPUC prior to moving forward with any type of deal. That seamed odd to me and they would need to have a deal in hand or have some parameters of a deal structure to get any type of approval. I imagine that SDG&E is concerned that the shareholders get stuck with any risk if the do enter into a deal and it is found not to be prudent (not to mention the fact that they have had trouble pulling a trigger or even pointing in the past). Have any of the other utilities tried something like this or does the CPUC give a pre-approval or a declaratory order of this nature. Does the CPUC have process in place to do this. Any thoughts.