24 Jul 2001, 01:16 UTC
RE:
- From
- Bill Williams III bill.williams@enron.com
- To
- Kate Symes
- Date
- Mon, 23 Jul 2001 18:16:04 -0700 (PDT)
Baruuuh?
Quoted or forwarded from earlier messages
-----Original Message----- From: Symes, Kate Sent: Monday, July 23, 2001 3:14 PM To: DL-Portland Real Time Shift Subject: We have entered into another lending agreement with El Paso for Tuesday, 7/24. I've entered deals to show this in our system as a purchase from El Paso at $4 (fee for lending - to be changed if we end up actually purchasing from El Paso) and a sale to STSW. This is a 25 mw on peak schedule (tag entered by Lisa Gang) to be delivered at Palo Verde. We need to send 25 mws (zero price) to EPE real-time at PV to fulfil our part of the agreement. Following are the terms of these deals: 697528 - STWBOM buys EPE HLH @ PV 25 mw @ $4 (This price represents El Paso's fee for lending) 697536 - STWBOM sells STSW HLH @ PV 25 mw @ $68 Let me know if you have any questions. Thanks, Kate