Enron email

Algorithmic Indexing

5 Jun 2001, 16:29 UTC

RE: Unify Gas Performance Testing

From
Tony Dugger tony.dugger@enron.com
To
Tony Dugger, Georgia Ward, Tom Acton, Jacqueline P. Adams, Robert Allwein, Natalie Baker, Shanna Boudreaux, Kevin Brady, j..brewer@enron.com, Suzanne Calcagno, Tamara Carter, Joe A. Casas
and 117 more Suzanne Christiansen, Joann Collins, wes.dempsey@enron.com, Sabra L. Dinari, Ted Evans, Brenda H. Fletcher, Cynthia Franklin, Mary Theresa Franklin, Clarissa Garcia, Steve Gillespie, Tammy Gilmore, Donna Greif, Shannon Groenewold, Lia Halstead, Meredith Homco, Lisa Kinsey, Shahnaz Lakho, Victor Lamadrid, Kirk Lenart, Daniel Lisk, Scott Loving, Hillary Mack, Mark McCoy, Shelly Mendel, t..muzzy@enron.com, Kimberly S. Olinger, Chris Ordway, Cora Pendergrass, Richard Pinion, Carlos J Rodriguez, Christina Sanchez, Mark L. Schrab, Patti Sullivan, Robert Superty, jan.sutherland@enron.com, Edward Terry, Alvin Thompson, jesse.villarreal@enron.com, Jessica White, Jason Wolfe, tracy.wood@enron.com, Jeanne Wukasch, Mary Alba, Bryce Baxter, b..boxx@enron.com, Janine Cashin, Shielah Castro, Pamela Chism, Audrey Cook, john.couvillon@enron.com, Paul Couvillon, Valerie Curtis, Max Doner, Scott Dozier, Mary Ellenberger, Laurie Ellis, David W. Eubanks Jr., Linda J. Ewing, Rebecca Griffin, Cynthia Hakemack, Priscilla Hamic, Melanie Harwell, Katherine Herrera, charles.howard@enron.com, Charles Jacobs, gregg'.'lenart@enron.com, Buddy Majorwitz, Genaro Mendoza, Michael Mousteiko, Donnie Myers, Doug Nelson, Joanie H Ngo, Megan Parker, jack.peebles@enron.com, Vivien Pham, lashanda.poledore@enron.com, Wade R. Price, Tess Ray, y..resendez@enron.com, Charlene Richmond, s..saladino@enron.com, Darla Saucier, willie.stewart@enron.com, s.thomas@enron.com, tricia.truong@enron.com, lisa.valderrama@enron.com, larry.aguirre@enron.com, Sherry Anastas, Gloria G Barkowsky, Antoinette Beale, milton.bolanos@enron.com, willie.brooks@enron.com, rosa.brown@enron.com, eric.calub@enron.com, Howard B Camp, Lee Ann Chance, Mary Comello, bob.fisher@enron.com, ron'.'gaskey@enron.com, alton.honore@enron.com, Marlo C James, ryan.keith@enron.com, Karen Lindley, Mark Mcclure, jack.mitchell@enron.com, Thu Nguyen, Hakeem Ogunbunmi, jennifer.pattison@enron.com, Leslie Robinson, Sherlyn Schumack, Christopher Spears, Stephen Swisher, alfonso.trabulsi@enron.com, Kimberly Vaughn, Joyce Viltz, jason.vogler@enron.com, Rita Wynne
Cc
Brian Ripley, jill.hopson@enron.com, Regan M. Smith
Bcc
Brian Ripley, jill.hopson@enron.com, Regan M. Smith
Date
Tue, 5 Jun 2001 09:29:41 -0700 (PDT)
Today's Performance Test has been delayed 1 hour.  It will begin at 1:00.

Sorry for the delay.
Quoted or forwarded from earlier messages
-----Original Message-----
From: 	Dugger, Tony  
Sent:	Tuesday, June 05, 2001 9:47 AM
To:	Ward, Georgia; Acton, Tom; Adams, Jacqueline P.; Allwein, Robert; Baker, Natalie; Boudreaux, Shanna; Brady, Kevin; Brewer, Stacey J.; Calcagno, Suzanne; Carter, Tamara; Casas, Joe A.; Christiansen, Suzanne; Collins, Joann; Dempsey, Wes; Dinari, Sabra L.; Evans, Ted; Fletcher, Brenda H.; Franklin, Cynthia; Franklin, Mary Theresa; Garcia, Clarissa; Gillespie, Steve; Gilmore, Tammy; Greif, Donna; Groenewold, Shannon; Halstead, Lia; Homco, Meredith; Kinsey, Lisa; Lakho, Shahnaz; Lamadrid, Victor; Lenart, Kirk; Lisk, Daniel; Loving, Scott; Mack III, Hillary; McCoy, Mark; Mendel, Shelly; Muzzy, Charles T.; Olinger, Kimberly S.; Ordway, Chris; Pendergrass, Cora; Pinion, Richard; Rodriguez, Carlos; Sanchez, Christina; Schrab, Mark L.; Sullivan, Patti; Superty, Robert; Sutherland, Jan; Terry, Edward; Thompson, Alvin; Villarreal, Jesse; White, Jessica; Wolfe, Jason; Wood, Tracy; Wukasch, Jeanne; Alba, Mary; Baxter, Bryce; Boxx, Pam B.; Cashin, Janine; Castro, Shielah; Chism, Pamela; Cook, Audrey; Couvillon, John; Couvillon, Paul; Curtis, Valerie; Doner, Max; Dozier, Scott; Ellenberger, Mary; Ellis, Laurie; Eubanks Jr., David W.; Ewing, Linda J.; Griffin, Rebecca; Hakemack, Cynthia; Hamic, Priscilla; Harwell, Melanie; Herrera, Katherine; Howard, Charles; Jacobs, Charles; 'Lenart, Gregg'; Majorwitz, Buddy; Mendoza, Genaro; Mousteiko, Michael; Myers, Donnie; Nelson, Doug; Ngo, Joanie; Parker, Megan; Peebles, Jack; Pham, Vivien; Poledore, LaShanda; Price, Wade R.; Ray, Tess; Resendez, Isabel Y.; Richmond, Charlene; Saladino, Jane S.; Saucier, Darla; Stewart, Willie; Thomas, Yolanda S; Truong, Tricia; Valderrama, Lisa; Aguirre, Larry; Anastas, Sherry; Barkowsky, Gloria; Beale, Antoinette; Bolanos, Milton; Brooks, Willie; Brown, Rosa; Calub, Eric; Camp, Howard; Chance, Lee Ann; Comello, Mary; Fisher, Bob; 'Gaskey, Ron'; Honore, Alton; James, Marlo; Keith, Ryan; Lindley, Karen; McClure, Mark; Mitchell, Jack; Nguyen, Thu; Ogunbunmi, Hakeem; Pattison, Jennifer; Robinson, Leslie; Schumack, Sherlyn; Spears, Christopher; Swisher, Stephen; Trabulsi, Alfonso; Vaughn, Kimberly; Viltz, Joyce; Vogler, Jason; Wynne, Rita
Cc:	Ripley, Brian; Hopson, Jill; Smith, Regan M.
Subject:	RE: Unify Gas Performance Testing
Importance:	High

************************* REMINDER ****************************

Gas Performance Test TODAY from 12:00 p.m. - 2:00 p.m.	Logistics 		12:00 p.m. - 2:00 p.m.
								Vol. Mgmt		12:20 p.m. - 2:00 p.m.
								Settlements		  1:00 p.m. - 2:00 p.m.

Menu Option: 	Unify2k (Gas)
Server: 		Unify2k Gas Production
Data: 		May 29, 2001
Gas Day:    	May 29, 2001


Test team members will be on your floors prior to the start of your test and will provide handouts to capture performance metrics.

Thank you, 
TD



 -----Original Message-----
From: 	Ward, Georgia  
Sent:	Friday, June 01, 2001 3:28 PM
To:	Acton, Tom; Adams, Jacqueline P.; Allwein, Robert; Baker, Natalie; Boudreaux, Shanna; Brady, Kevin; Brewer, Stacey J.; Calcagno, Suzanne; Carter, Tamara; Casas, Joe A.; Christiansen, Suzanne; Collins, Joann; Dempsey, Wes; Dinari, Sabra L.; Evans, Ted; Fletcher, Brenda H.; Franklin, Cynthia; Franklin, Mary Theresa; Garcia, Clarissa; Gillespie, Steve; Gilmore, Tammy; Greif, Donna; Groenewold, Shannon; Halstead, Lia; Homco, Meredith; Kinsey, Lisa; Lakho, Shahnaz; Lamadrid, Victor; Lenart, Kirk; Lisk, Daniel; Loving, Scott; Mack III, Hillary; McCoy, Mark; Mendel, Shelly; Muzzy, Charles T.; Olinger, Kimberly S.; Ordway, Chris; Pendergrass, Cora; Pinion, Richard; Rodriguez, Carlos; Sanchez, Christina; Schrab, Mark L.; Sullivan, Patti; Superty, Robert; Sutherland, Jan; Terry, Edward; Thompson, Alvin; Villarreal, Jesse; White, Jessica; Wolfe, Jason; Wood, Tracy; Wukasch, Jeanne; Alba, Mary; Baxter, Bryce; Boxx, Pam B.; Cashin, Janine; Castro, Shielah; Chism, Pamela; Cook, Audrey; Couvillon, John; Couvillon, Paul; Curtis, Valerie; Doner, Max; Dozier, Scott; Ellenberger, Mary; Ellis, Laurie; Eubanks Jr., David W.; Ewing, Linda J.; Griffin, Rebecca; Hakemack, Cynthia; Hamic, Priscilla; Harwell, Melanie; Herrera, Katherine; Howard, Charles; Jacobs, Charles; Lenart, Gregg; Majorwitz, Buddy; Mendoza, Genaro; Mousteiko, Michael; Myers, Donnie; Nelson, Doug; Ngo, Joanie; Parker, Megan; Peebles, Jack; Pham, Vivien; Poledore, LaShanda; Price, Wade R.; Ray, Tess; Resendez, Isabel Y.; Richmond, Charlene; Saladino, Jane S.; Saucier, Darla; Stewart, Willie; Thomas, Yolanda S; Truong, Tricia; Valderrama, Lisa; Aguirre, Larry; Anastas, Sherry; Barkowsky, Gloria; Beale, Antoinette; Bolanos, Milton; Brooks, Willie; Brown, Rosa; Calub, Eric; Camp, Howard; Chance, Lee Ann; Comello, Mary; Fisher, Bob; Gaskey, Ron; Honore, Alton; James, Marlo; Keith, Ryan; Lindley, Karen; McClure, Mark; Mitchell, Jack; Nguyen, Thu; Ogunbunmi, Hakeem; Pattison, Jennifer; Robinson, Leslie; Schumack, Sherlyn; Spears, Christopher; Swisher, Stephen; Trabulsi, Alfonso; Vaughn, Kimberly; Viltz, Joyce; Vogler, Jason; Wynne, Rita
Cc:	Ripley, Brian; Hopson, Jill; Smith, Regan M.; Dugger, Tony
Subject:	Unify Gas Performance Testing

Below you will find a schedule for performance testing that is scheduled for Tuesday June 5, 2001 from 12:00 - 2:00.  IT floor support will show up about 20 minutes prior to your groups start time.

Please read and if you have any questions contact me.

Thanks-
Georgia
x3-9974

Unify Gas Performance Testing
User Test - Schedule/Script


June 5, 2001	Begin 12:00 p.m.		End 2:00 p.m. (CST)

Menu Option: Unify2k (Gas)
Server: Unify2k Gas Production
Data: May 29, 2001
Gas Day: TBD

Logistics  	(12:00 - 2:00 CST)

	I.T. Team
	Sitara Bridge Process	-	Begins @ 11:30 for gas flow on May 19th 
	EDI -				Begins @ 12:15 Diane Niestrath will execute 
all phases of EDI to generate system load.  Nominations, Quick Response, and Notifications files from 01/30/01 between 10:00 and 12:00 will be processed.  Scheduled Quantities will not be processed since it is not executed between 10:00 and 12:00 during bid-week.
	
	User Team
	Login				12:00 (CST)
	
	Send EDI 		(users can send EDI Nominations, but will not be able to 
use the Quick Response Report, or the Schedule Quantity Log - see EDI above)

	Test Scripts will be distributed by the IT floor support team prior to the start of the test.
	
Volume Management 	(12:20 - 2:00 CST)

I.T. Team
	POPS Revenue Bridge -	Begins @ 12:20
	
	User Team
	Login			12:20 (CST)

Test Scripts will be distributed by the IT floor support team prior to the start of the test.



Settlements 	(1:00 - 2:00 CST)

	I.T. Team
	LoadRunner -			The I.T. Team will evaluate the system load 
between 1:00 and 1:30.  If less than 100 users are logged in or the system load is determined to be low, LoadRunner scripts will begin executing at 1:30 in order to generate additional system load.

User Team
Login				1:00 (CST)

Test Scripts will be distributed by the IT floor support team prior to the start of the test.





Georgia Ward
ENW - Development Support - QA
(713)853-9974