25 Jan 2002, 21:34 UTC
FW: Refrigerant compressor
- From
- Jerry Graves jerry.graves@enron.com
- Date
- Fri, 25 Jan 2002 13:34:31 -0800 (PST)
Here is the latest on the compressor at Garner. Jerry
Quoted or forwarded from earlier messages
-----Original Message----- From: Garner, Team Sent: Friday, January 25, 2002 3:19 PM To: Graves, Jerry; Thomas, Steve Subject: Refrigerant compressor York International will be in Monday Jan. 29 to begin preping the refrigerant compressor for transport. There plan is to load the compressor on truck Monday the 4th of Feb. Yorks estimate for repair/test and back to us at 6 to 8 weeks. So we don't look for the compressor to be back till the 1st week of April as long as everything goes according to plans.